Recycling Industry
Australia Cancels $24.7M Solar Panel Recycling Pilot Tender
Australia cancelled its $24.7 million National Solar Panel Recycling Pilot tender on 10 November, citing undisclosed industry changes, as end-of-life panel volumes head toward 50 million by 2035.

Waypoints
The $24.7 million (USD 16.9 million) pilot tender was cancelled on 10 November 2026 without a contract award.
The tender, released April 2026, was suspended in May 2026 after a procurement complaint against DCCEEW.
The pilot targeted collection of up to 250,000 decommissioned panels from about 100 sites across Australia.
An estimated 3 million panels reached end-of-life in 2025, projected to grow to 50 million by 2035.
The administrator contract was to run from May 2026 to June 2027, with possible extension.
Australia's $24.7 million (USD 16.9 million) National Solar Panel Recycling Pilot procurement is dead — cancelled on 10 November without a contract ever being awarded, on the same day the government lifted a six-month suspension on the process.
The Department of Climate Change, Energy, the Environment and Water (DCCEEW) scrapped the search citing undisclosed "changes to the industry" since the tender's release in April 2026. The government is now considering "next steps" for procuring an administrator for the pilot. What those next steps look like, and when, remains unstated.
What happened to the tender?
The timeline is tight and telling.
- April 2026: DCCEEW releases the tender for a National Solar Panel Recycling Pilot (NSPRP) administrator.
- May 2026: The procurement is suspended after a complaint triggers an investigation.
- 10 November 2026: The suspension lifts — and the procurement is cancelled the same day, no contract awarded.
The complaint centred on the settings and rules of the procurement process itself. Details of the complaint and the investigation's findings are not public, so the record shows a process that stalled on process, not on price or capability.
The administrator contract was originally meant to begin by May 2026 and run until June 2027, with the possibility of extension. In other words, the pilot's entire delivery window has now been consumed by the suspension and cancellation.
What was the pilot supposed to do?
The procurement sought a single supplier to arrange, manage, deliver and report to government on the NSPRP. That supplier would have carried the concrete logistics of the scheme:
- Arrange collection of up to 250,000 decommissioned panels from around 100 sites across Australia;
- Ensure panels are safely aggregated;
- Manage transport;
- Deliver the panels into recycling.
That's a national, multi-site collection build-out for a material stream that currently has no dedicated federal recovery infrastructure at this scale. The cancellation removes the only committed federal funding vehicle of this size for end-of-life panel recovery on the table right now.
Why the volumes matter
The government's own numbers frame the stakes. An estimated 3 million panels reached end-of-life in Australia in 2025. By 2035, that figure could reach 50 million panels — a waste mountain that Australian recycling advocates have warned requires product stewardship law now, not later.
Against that curve, the pilot's 250,000 panels were always a fraction of the flow — roughly 8% of a single year's 2025 end-of-life volume. But it was the federal government's flagship commitment to building collection and recycling capacity for the stream, and its cancellation leaves the timeline for any replacement unclear.
For recyclers, site operators and state agencies watching for a national collection framework, the signal is mixed: the money was real, the mechanism wasn't durable.
What decides what happens next
The open question is whether DCCEEW re-tenders the pilot under revised settings or folds it into a broader regulatory scheme — and whether Australia's stewardship push arrives before the 2035 volume spike does. The next milestone to watch is the government's announcement of those "next steps" for procurement.