CNPC Commissions 277.6-km CO2 Pipeline at Jilin Oilfield

CNPC's 277.6-km Jilin pipeline entered commercial operation with capacity for 3.3 million metric tons of CO2 a year, linking capture units to enhanced oil recovery.

CNPC Commissions China’s Longest CO2 Pipeline
CNPC Commissions China’s Longest CO2 Pipeline652234 / pixabay

Waypoints

  1. CNPC commissioned the 277.6-km, or 172.5-mile, Jilin Petrochemical-Jilin Oilfield CO2 pipeline.

  2. The line has a 14.5 MPa design pressure and capacity for up to 3.3 million metric tons per year.

  3. It runs from the Jinlan initial station through Jilin, Changchun and Songyuan to the Jilin Oilfield.

  4. Jilin Petrochemical's 800,000-ton-per-year CO2 recovery project reached full commissioning in October 2026.

  5. CNPC positions the operating line as a regional CCUS backbone but discloses no third-party contracts or connection schedule.

By Grace Kim

CNPC has commissioned a 277.6-kilometer carbon dioxide pipeline with capacity for 3.3 million metric tons a year at the Jilin Oilfield in Northeast China, establishing the country’s longest dedicated CO2 transmission corridor.

The Jilin Petrochemical-Jilin Oilfield line in Jilin Province entered commercial operation with a design pressure of 14.5 MPa. Its 277.6-kilometer, or 172.5-mile, route links upstream industrial capture facilities directly to subsurface injection sites.

A route from capture to injection

At the Jinlan initial station, the pipeline receives compressed carbon dioxide from Jilin Petrochemical’s capture units. It carries the supercritical stream northward through Jilin, Changchun and Songyuan to the Jilin Oilfield.

The line supports enhanced oil recovery and permanent geological storage at the oilfield. That gives the project two stated end uses, while one named industrial source and one oilfield destination anchor the operating asset.

Capacity and national performance records

CNPC said the trunk line sets domestic records for length, pipe diameter, operating pressure and volume capacity. The announcement discloses 277.6 kilometers of route, a 14.5 MPa design pressure and up to 3.3 million metric tons of annual throughput, but gives no numerical pipe diameter.

The operating asset combines a transport service with a four-part national performance claim. Three benchmarks come with disclosed measurements; the diameter claim does not, which leaves the scope of that record unspecified in CNPC’s announcement.

The 3.3 million metric-ton figure defines transport capability, not current flow. CNPC did not claim that the line already carries that volume, and its announcement gives no pipeline commissioning date, utilization rate, tariff or capital cost.

A named source for a larger trunk

Jilin Petrochemical’s 800,000-ton-per-year CO2 recovery project reached full commissioning in October 2026. CNPC identified that facility as the stable upstream feedstock behind the pipeline, connecting an operating recovery unit to a high-pressure line built for substantially greater annual throughput.

On the company’s stated figures, the source project’s annual recovery scale sits below the pipeline’s maximum annual transport capacity. CNPC did not disclose current utilization, contracted third-party tonnage or a schedule for adding supply, although it says the line provides spare transport capacity for additional industrial emitters as regional capture projects scale.

The announcement also gives no allocation between enhanced oil recovery and permanent geological storage. For prospective industrial suppliers, it identifies the Jinlan entry station and the line’s aggregate capacity, but not individual connection points or reserved volumes.

The three-city route concentrates the operating test in Jilin Province rather than across the wider region. CNPC has demonstrated the transport and injection link at one industrial hub; it has yet to show a multi-customer system.

What changes for Jilin’s oilfield and regional emitters?

For the Jilin Oilfield, the change is an operating high-pressure link between petrochemical capture and enhanced oil recovery, with permanent geological storage as the second stated function. For industrial emitters across Northeast China, CNPC is offering proximity to spare trunk capacity, but the announcement names no connected third parties or committed delivery volumes.

CNPC positioned the high-pressure line as a "central transmission backbone" for a broader regional carbon capture, utilization and storage industrial cluster. That wider cluster remains a stated development plan; the commissioned infrastructure comprises the 277.6-kilometer pipeline and its connection to Jilin Petrochemical.

The next commercial milestone

The next milestone is commercial rather than geographic: CNPC needs third-party emitters, connection projects and commissioning dates to turn spare capacity into a regional network. Its announcement provides no permit deadline, regulator or binding expansion schedule, so a signed customer agreement or a disclosed third-party connection will offer the first verifiable test of the cluster plan.

Until that evidence appears, the 277.6-kilometer line demonstrates completed CO2 transport infrastructure between a named capture source and the Jilin Oilfield. It also gives CNPC a platform for additional industrial supply, but not yet proof that third parties will connect at scale.

via cnpc.com.cn (Original)

Share this article:

More from Grace Kim

Grace Kim

Show full bio

Market editor covering money, funding and market shifts around Circular economy and the environmental industry at Circular Wire.

560 articles

Nearby routes

« Previous articleNext article »