Compliance & Policy

Ohio board approves 800 MW natural-gas plant for Ashville data center

Ohio approved an 800 MW gas plant for EdgeConneX’s Ashville data center despite 81% local voter opposition. Opponents have 30 days to seek reconsideration before a possible Ohio Supreme Court appeal.

Ohio OKs gas plant for data centers despite local voter backlash
Ohio OKs gas plant for data centers despite local voter backlashRalphs_Fotos / pixabay

Waypoints

  1. The Ohio Power Siting Board approved an 800 MW natural-gas plant in Ashville on Nov. 19.

  2. 81% of Ashville voters opposed the village government’s agreement with EdgeConneX on Election Day.

  3. EdgeConneX agreed to pay up to $102 million for municipal, school and community work.

  4. The plant will serve the data center complex without connecting to the broader electric grid.

  5. Opponents have 30 days to seek reconsideration before a possible Ohio Supreme Court appeal.

By Daniel Okafor

The Ohio Power Siting Board approved an 800-megawatt natural-gas plant at its Nov. 19 meeting for EdgeConneX’s data center complex in the central Ohio village of Ashville. The plant will serve just the computing warehouses and will not connect to the broader electric grid.

On Election Day, 81% of Ashville voters opposed the village government’s agreement with EdgeConneX. Ashville was one of dozens of U.S. communities where residents rejected data centers, but the state permit proceeded.

The local result and the state decision now point in opposite directions.

What did the $102 million agreement cover?

The Ashville Village Council passed an April resolution backing the data center and gas plant after EdgeConneX agreed to pay up to $102 million to support municipal, school and community work. Some residents then gathered enough signatures to secure a referendum on overturning that resolution.

The arrangement gave the project local institutional backing even as residents organized against it.

What did the board find in its 108-page opinion?

The board found EdgeConneX met the statutory requirement that the project serve the public interest. Its 108-page opinion cited economic benefits, village council backing, local school district support and developer promises to limit noise and construction hours.

Regulators said conditions agreed by the village, developer and board staff addressed public concerns. They also acknowledged the Ashville vote but said the board could issue the permit regardless of the outcome.

The state permit therefore advances despite the local vote.

What concerns did the plant raise?

The plant site sits near homes, a playground, a park and a soccer field. State Rep. Tristan Rader, a Democrat and ranking minority member of the Ohio House Energy Committee, took part in the case as a nonvoting member of the Power Siting Board.

At the Nov. 19 meeting, Rader argued that the plant would cast a shadow over nearby communities while spewing health-harming pollution.

Across the U.S., energy-hungry data center developers are racing ahead with controversial plans for natural-gas-fired generation, placing Ashville inside a broader national race to meet data-center power demand.

Why do critics see a double standard?

Ohio applies more stringent requirements to wind and solar, even though those technologies emit zero air pollution. Rader said: “There’s a huge double standard for fossil fuels and renewables in the state of Ohio.”

Chris Tavenor, general counsel for the Ohio Environmental Council, which did not participate as a party, said: “In this case, the Board does the exact opposite, using those community benefits and conditions to justify ignoring local concerns.”

He called the outcome hypocritical because the board approved a natural-gas facility after denying renewable projects with less significant opposition.

Tavenor said the board has denied multiple solar projects when local opposition outweighed economic benefits, or proposed permit conditions aimed at addressing community concerns. Critics also fault the board for deferring to local governments when the broader public does not share their position.

  • In 2025, board staff recommended against the Grange Solar project in Logan County because local governments pushed back. A majority of people who submitted comments supported the solar farm, but the developer withdrew and pursued projects elsewhere.
  • Earlier this year, regulators rejected Crossroads Solar in Morrow County because all nearby local governments opposed it. The ruling described strong, united local opposition, though the developer said dozens of comments appeared fake. Its analysis found verifiable opponents were not overwhelming compared with supporters.

Board staff also reversed course on Crossroads, moving from support to opposition after one township changed its stance from neutral to opposed.

Those solar decisions sharpen the claim that Ohio treats gas generation more favorably than renewable projects.

How did the board apply the minimum-impact test?

Opponents argued that the gas plant failed a separate legal requirement for minimal environmental impact. EdgeConneX chose reciprocating internal combustion engines and simple-cycle natural-gas turbines over less-polluting combined-cycle turbines or fuel cells; those alternatives cost more at the time.

Regulatory staff argued that “minimum” does not mean the lowest possible environmental impact; the standard depends on a plant’s purpose, available technology and economics. The board agreed the project met the requirement.

The board then effectively punted to the Ohio Environmental Protection Agency, which is expected to issue air permits for the facility. The siting permit does not replace that separate EPA air-permit decision.

What happens next?

Project opponents have 30 days to ask the Power Siting Board for reconsideration. Unless the board changes its mind, an appeal to the Ohio Supreme Court could follow.

The next trigger is a reconsideration request within 30 days; without a board reversal, the permit dispute can move to the state’s highest court.

via canarymedia.com (Source)

Share this article:

More from Daniel Okafor

Daniel Okafor

Show full bio

Correspondent covering companies, deals and strategy in Circular economy and the environmental industry at Circular Wire.

573 articles

Nearby routes

« Previous article