Wallonia orders Google to stop work on 7.4-acre datacentre
Wallonia ordered Google to stop work on a nearly finished 7.4-acre datacentre after permit changes were revoked, with a Council of State ruling due Jan. 7.

Waypoints
Wallonia ordered Google to halt work on a nearly finished 3-hectare datacentre after the modified permit was revoked.
A 2024 permit covered three smaller air-cooled datacentres; a 2025 amendment sought one larger liquid-cooled building.
The revised cooling plan would draw 600 cubic metres of Sambre River water per hour.
Belgium’s Council of State is due to rule on Google’s appeal on Jan. 7.
Finland opened a criminal investigation in October and halted work pending environmental impact assessments.
Wallonia ordered Google to halt work on a nearly finished 3-hectare datacentre, with a ruling on its permit appeal due Jan. 7 from Belgium’s Council of State. Inspectors found that structural work had advanced without approval for major changes to the site’s planning permission.
What changed at the Aiseau-Presles site?
The building occupies about 3 hectares (7.4 acres) in a 50-hectare business park on the site of a former coalmine at Aiseau-Presles, roughly 15 km (9 miles) west of Charleroi in southern Belgium. It is one of three facilities Google originally planned there; only the consolidated facility is identified as nearly finished.
“Inspectors visited the site and observed that the building was almost finished, with the structural work completed, even though the permit had been refused,” Wallonia regional official Raphaël Stokis told public broadcaster RTBF.
Stokis said the 300 workers had received a verbal stop order, which the regional administration later confirmed to Google in writing. Google said in a statement that it remained committed to maintaining an open and collaborative dialogue with the regional authorities.
For contractors, physical progress has now outrun the permit. The shell is almost complete, but the company still needs an enforceable planning basis for the modified design before it can complete the project.
Which permit was supposed to cover the project?
Google’s 2024 permit authorised three smaller air-cooled datacentres. In 2025, the company applied to merge two into one much larger facility and switch to liquid cooling, drawing 600 cubic metres an hour from the nearby Sambre River.
That withdrawal rate equals 10,000 litres per minute. It makes the cooling change a regional water-demand issue as well as a planning dispute, particularly after the regional administration revoked the amended permit over drought concerns.
The administration initially approved the amendments in April. Residents and protest groups appealed, and in August Wallonia infrastructure minister François Desquesnes revoked the modified permit.
The reported figures do not include computing capacity for either the near-complete structure or the original three-building proposal. The measurable footprint is 3 hectares, while the resource requirement at issue is the proposed hourly river-water draw; the permit dispute concerns both the physical expansion and its water supply.
Why has the project become an enforcement case?
Greenpeace earlier in the week published a report with drone footage that it said showed Google continuing work despite a lack of correct permits. The environmental group also filed an emergency appeal with local planning authorities.
Greenpeace argued that construction of energy-intensive facilities could not go unnoticed as climate risks intensify in the region. The group said the footage documented the sequence now at the center of enforcement: revocation in August followed by continued site work.
On Friday, regional government spokesperson Nicolas Yernaux told Agence France-Presse that the government was submitting a report to public prosecutors alleging “a major offence: the illegal construction of a building covering 3 hectares.” The referral puts the disputed construction before public prosecutors and runs alongside, rather than replacing, Google’s administrative appeal.
What happens next at Aiseau-Presles?
Google has appealed Desquesnes’s revocation to Belgium’s Council of State. A ruling is due on Jan. 7.
A ruling for Google would clear the modified permit as an administrative barrier to restarting work. A ruling against it would leave the construction stop in place, while the prosecutor’s review would continue as a separate issue.
The Jan. 7 decision therefore sets the immediate threshold for the site: whether Google can resume work under the amended permission or must keep the nearly complete structure under a stop order. The prosecutor’s review remains a separate track.
How does this compare with Google’s other European projects?
The case is the latest confrontation facing Google in Europe as large technology companies build datacentres to support the AI boom. In October, Finland opened a criminal investigation into possible breaches of environmental law at a planned Google datacentre in the country’s rural north. Work there has been halted until environmental impact assessments are complete.
For project developers, the Belgian dispute shows how planning permission can become a stop-work order when a company changes facility scale or cooling plans. The Belgian and Finnish cases also place water supply and environmental assessment beside construction progress rather than treating them as later compliance issues.
The decisive near-term milestone is Jan. 7: the Council of State ruling will determine the permit path for resumption, while the major-offence report remains before public prosecutors.