Compliance & Policy
Whitehall floats scrapping Natural England weeks after its Avonmouth objection
Natural England and the EA objected to a 40MW datacentre 600m from the Severn estuary SPA; weeks later, ministers suggested scrapping both agencies. Bristol council wants a full EIA.

Waypoints
Natural England objected to a 40MW datacentre at Avonmouth, 600m from the Severn estuary special protection area
More than 300 datacentres await grid connection, representing 73GW of demand — nearly double UK peak winter demand
Over 4,000 people objected to the Avonmouth datacentre's construction
Louise Haigh indicated Natural England and the Environment Agency could be abolished, with duties handed to ministers or devolved
The Wildlife Trusts launched a petition to save Natural England, citing protection work since the 1940s
More than 4,000 objections, two agency interventions and one threatened abolition: that is the current ledger on the 40MW AI datacentre proposed at Avonmouth, near Bristol — a project Natural England and the Environment Agency both urged Bristol city council to refuse, weeks before a minister suggested both bodies could be scrapped.
The sequencing is what matters here. Earlier this month, Natural England advised the council that the datacentre could cause "disturbance and displacement" to rare and vulnerable bird species within the Severn estuary special protection area, which sits just 600 metres from the site. A second protected site, Hallen Marsh, lies only 270 metres away — and Natural England said the developers had not accounted for it in their noise pollution assessment.
Then, this week, Louise Haigh — the de facto deputy prime minister — blamed quangos including Natural England for blocking development and indicated both agencies could be abolished, with their responsibilities handed to ministers or devolved.
What does each objection actually say?
The two agency positions are distinct, and both are material to the planning file:
- Natural England — significant intervention urging refusal of planning permission, on grounds of threat to protected wildlife and habitats at one of the UK's most important sites for migratory birds, within 600 metres of the site.
- Environment Agency — objection on flooding risk, noting the site sits on a high-risk flood plain and raising concerns that people would not be able to take safe refuge in the event of a deluge. It also flagged that developers had provided no information on the level of water use, or on the risk of pollution from land contamination to controlled waters.
Bristol council's own position pushes in the same direction. It said the proposal was "likely to give rise to significant environmental effects" and wants the developers to carry out a full environmental impact assessment.
Why this one project carries national weight
The Avonmouth case is a single application, but it sits inside a much larger pipeline. Hundreds of AI datacentres are planned across the UK, with more than 300 waiting in the queue to connect to the electricity grid — representing 73GW of demand, almost double the peak winter energy demand for the entire country.
They face considerable environmental and sustainability issues: high energy use, pollution, encroachment on protected habitats, and emissions from the fossil fuel power stations many developers want to install while waiting for grid connections.
To side-step local democracy, the government is allowing datacentre developers to use the nationally significant infrastructure projects (NSIP) regime, with the secretary of state acting as the decision maker.
Natural England has raised concerns about the wider rollout too. In its response to the government's draft datacentre national policy statement, it said AI datacentres were a relatively new development type whose full environmental impacts were still being understood, and it highlighted the potential impact on rare and vulnerable species from overabstraction of waterways to meet datacentres' cooling and operational demands. It urged a precautionary approach.
Did the objection trigger the abolition threat?
Government sources deny it. They say neither Natural England's objection to Avonmouth nor its precautionary stance on widespread datacentre construction influenced Haigh's announcement that the agency could be scrapped.
Craig Bennett, chief executive of the Wildlife Trusts, reads the signal differently. He said the threatened abolition was a worrying sign of an attack on environmental regulation, adding: "Regulatory arm's-length bodies like Natural England are set up to implement the law of parliament. If we want decisions made about nature on the basis of science rather than the very last private corporate or vested interest that a minister has spoken to, then we have independent arm's-length bodies like Natural England."
Mary Stevens, an AI campaigner at Friends of the Earth, made the practical case for keeping the current structure: "Natural England was doing its job brilliantly here as an independent adviser. I would have no confidence if this was a government minister doing the work because they would not be acting independently to protect nature."
The Wildlife Trusts have launched a petition to save Natural England, arguing the current body and its predecessors have been vital protectors of wildlife, land, water and sea across England since the 1940s.
The developer's response
Rivington Energy, which is developing the datacentre, said it acknowledges the feedback from both agencies and welcomes the opportunity to keep working constructively with consultees through the planning process. It said substantial environmental and technical assessment work has already been undertaken, additional studies are being prepared in response to the comments received, and a detailed environmental statement is being prepared to support the next stage of project assessment.
A government spokesperson said: "Datacentres are essential to our economy, but their development must protect the environment and benefit local communities. Developers must meet planning requirements, with local authorities assessing environmental impacts, and then deciding on local applications."
The near-term milestones are now fixed: Rivington's environmental statement submission, the council's decision on whether a full EIA is required, and Haigh's follow-through — or retreat — on abolishing the two bodies that filed the objections.