The IEA projects datacentres will consume twice as much electricity by 2030, with AI accounting for three-quarters of the increase.
AI datacentres could add 350 terawatt-hours of annual electricity use, more than Great Britain’s total consumption.
Datacentre emissions are on track to rise 70% by 2030.
The existing global datacentre stock is 120GW, with 80% in China, the United States and the EU; another 120GW is planned by 2030.
About 180GW of new gas-fired capacity linked to US datacentres was planned in August, compared with 11GW in Canada.
The global datacentre stock stands at 120GW, and the Paris-based International Energy Agency expects sector emissions to rise 70% by 2030.
By Olivia Hart
What is driving electricity demand?
The IEA expects global datacentres to consume twice as much electricity by 2030 as they do now, with artificial intelligence accounting for three-quarters of that increase. AI datacentres alone could add an extra 350 terawatt-hours of electricity each year. That amount exceeds Great Britain’s total annual electricity consumption.
The arithmetic is blunt. The agency expects appetite for fossil fuels to grow even faster than renewable deployment, particularly in the United States and China, where AI expansion is driving new generation.
Takeaway: AI creates most of the additional load, and the fuel used to serve it will decide the sector’s emissions.
How much capacity is operating?
The IEA based its forecasts for the notoriously opaque industry on annual global shipments of AI servers, which have climbed eighteen-fold since 2020. It also used space-based imagery to track the buildout of 93 large “AI factories” worldwide.
Its analysis says global datacentre capacity rose tenfold in the last 24 months to 17GW. The 93 AI factories were likely to have a combined capacity of about 50GW after completion.
Separately, the agency put the existing global stock of datacentres, including those with AI-optimised servers, at 120GW. China, the United States and the European Union hold 80% of that installed capacity.
The IEA central base case calls for developers to build another 120GW by the end of the decade. Three-quarters of that planned capacity will consist of AI datacentres.
Takeaway: Another 120GW is planned by 2030, and three-quarters of it is earmarked for AI.
Which power mix will datacentres use?
Datacentre developers have emerged as the world’s largest corporate buyers of renewable energy. They buy renewable power to help fuel servers at datacentres connected to local grids. That buying power has not prevented the expected acceleration in fossil generation.
By the end of the decade, the IEA expects coal to supply around half of the electricity used by China’s AI datacentres. Renewables will supply most of the remainder, nuclear reactors smaller amounts, and gas plants very little.
In contrast, the IEA expects gas to supply about 60% of electricity for United States datacentres by 2030. In the European Union, renewables should provide about 70%, followed by nuclear power, gas generation and a very small amount of coal.
Takeaway: China leans on coal, the United States on gas, and the European Union on renewables.
How large is the gas buildout?
In August, the IEA identified plans for about 180GW of new gas-fired power plants linked to United States datacentres. That amount is almost as much new capacity as the European Union’s entire installed gas fleet.
The appetite for gas power among United States datacentre developers is more than 16 times higher than in Canada, where the IEA identified plans for 11GW. Across the rest of the world, AI developers have proposed new gas plants with a combined capacity of just 4GW.
Renewables are expected to carry a greater role outside the United States and China, which explains the small gas pipeline elsewhere. That pipeline has a clear center of gravity: the United States.
Takeaway: The disclosed gas-expansion pipeline is heavily concentrated in the United States.
What could change the forecast?
The IEA’s annual report says the energy future is less certain after the Middle East war, which the agency calls the greatest energy market disruption in history. IEA Executive Director Fatih Birol said: “I don’t see any credible pathway for the energy world to return to the way it was before.”
Government policy after the crisis will reshape the energy system as it meets rising demand from a growing global population, more air-conditioning and the AI economy. Those decisions will determine how much new generation comes from coal, gas, renewables and nuclear.
Takeaway: Post-crisis energy policy will set the fuel mix for new datacentre demand.
What milestone comes next?
The IEA central base case calls for another 120GW of datacentre capacity by the end of the decade, three-quarters of it for AI. The decisive test is the power mix attached to those projects and the policy decisions that follow the energy crisis.
Post-crisis energy policy now sits upstream of the coming buildout. Governments can set the power mix for the 120GW planned by 2030, but the IEA currently assigns the largest fossil shares to China and the United States. The forecast is clear; the policy is not.
Takeaway: The 2030 power mix for 120GW of planned capacity will show whether the projected 70% emissions rise takes hold.