Compliance & Policy

DESNZ counts 4.45 million retrofits as ECO4 gets nine more months

DESNZ confirms 4,455,308 retrofit measures across 2,593,687 Great Britain homes, as ECO4's deadline extends nine months to 31 December 2026 amid falling monthly install volumes.

UK DESNZ Releases Headline Statistics on Household Energy Efficiency Retrofits and Scheme Delivery
UK DESNZ Releases Headline Statistics on Household Energy Efficiency Retrofits and Scheme DeliveryLife-Of-Pix / pixabay

Waypoints

  1. DESNZ reports 4,455,308 total retrofit measures across 2,593,687 Great Britain properties as of September 2026.

  2. ECO4 deadline extended nine months, from 31 March 2026 to 31 December 2026.

  3. Monthly ECO4 installs fell to 2,567 in September 2026, down from peaks above 26,000 in 2023-2024.

  4. Cumulative ECO expenditure since 2013 stands at £11,496.6 million, including £654.1 million administrative overheads.

  5. ECO4 average cost per pound of lifetime bill saving: £21.04 overall, £16.17 for social housing.

Great Britain's household retrofit ledger now stands at 4,455,308 installed measures across 2,593,687 unique properties, according to the Department for Energy Security and Net Zero's accredited headline statistics published on 26 November 2026. The same release confirms a nine-month extension of the ECO4 supplier obligation, pushing its statutory end date from 31 March 2026 to 31 December 2026.

The dataset, which tracks delivery from January 2013 through September 2026 under successive Energy Company Obligation cycles, gives the trade a full accounting of the current ECO4 round and a clear sense of where the pipeline is slowing. Not all of it is encouraging.

What has ECO4 actually delivered?

Since launching in April 2022, ECO4 has delivered 1,043,418 measures across 304,814 properties. That figure comprises:

  • 952,495 core ECO4 installations
  • 30,228 measures delivered during the ECO3 interim transitional window
  • 60,695 approved surplus action measures carried forward from ECO3

Monthly velocity tells a harder story. Installation numbers peaked in 2023 and 2024 at more than 26,000 measures per month. In mid-2026 they fell to 2,710 in July, 2,650 in August and 2,567 in September. DESNZ statisticians note that recent months remain provisional and subject to upward revision as installers submit notification records.

The programme's shape matters as much as its size. ECO4 mandates multi-measure, whole-house retrofits under PAS 2035/2030 standards, aiming to move properties in EPC bands E, F and G into band C or higher.

Which measures dominate the pipeline?

Heating controls lead the table. DESNZ reports 504,191 heating control installations — thermostats, TRVs and zone controls — of which 143,904 came through Flexible Eligibility (Flex) referrals. Loft and roof insulation follows at 138,882 measures, then micro-generation at 115,168.

Within micro-generation, the split runs:

  • 67,525 rooftop solar PV systems
  • 46,399 air-source heat pumps
  • 692 hybrid heat pump systems
  • 551 ground-source heat pump connections

Solid wall insulation totals 88,663 measures, dominated by 55,845 internal wall systems against 31,181 external wall projects. Cavity wall insulation sits at 49,196, with a notable 15,278 of those in social housing — the one category where social stock out-delivers private E, F and G homes. First-time central heating adds 20,187 installations.

Cost reporting covers January 2013 to June 2026: cumulative expenditure across all ECO iterations reached £11,496.6 million, split between £10,842.5 million in direct contractor delivery costs and £654.1 million in administrative overheads. For ECO4, the average cost per pound of lifetime annual bill saving was £21.04 across suppliers — £21.11 for private tenure band E, F and G properties and £16.17 for social housing retrofits. Social landlords, it appears, buy efficiency more cheaply.

Why the deadline moved?

The Electricity and Gas (Energy Company Obligation) Order 2022 set a four-year timeline from 1 April 2022 to 31 March 2026, with an annual expenditure expectation of roughly £1 billion from major gas and electricity suppliers. Delivery hit supply chain constraints and the administrative weight of whole-house retrofit standards. Following consultation, DESNZ confirmed the nine-month extension, giving suppliers runway to meet allocated bill savings targets and to remediate defective installations without displacing planned new volumes.

Ofgem administers the scheme, audits supplier compliance and maintains the official register of verified measures. It also runs the complementary Great British Insulation Scheme, which delivers single insulation measures to households in lower council tax bands.

Quality assurance has tightened. Reviews of solid wall insulation installed under ECO4 and GBIS prompted TrustMark and regulators to institute heightened compliance screening, mandatory site inspections and contractor find-and-fix protocols, covering ventilation adequacy, moisture management and structural anchorage before measures count toward supplier obligations. The retrofit sector is now doing remediation and delivery at the same time.

What happens next?

The milestone calendar is fixed. Obligated suppliers must complete and notify all qualifying measures to Ofgem by 31 December 2026. Quarterly delivery reporting in Q1 2027 will publish comprehensive supplier cost filings and delivery reconciliations. DESNZ's next full national statistics tables follow in summer 2027, with audited annual revisions. The Warm Homes Plan then phases in, shifting local delivery frameworks toward municipal authority leadership.

The binding constraint is the calendar, not the ledger. Everything now resolves on what suppliers can remediate and install before the 31 December deadline closes the ECO4 account.

via casrai.org (Source)

More from Olivia Hart