Cleantech & Investment
New York Awards Contracts for 950 MW of Grid Batteries in Storage Push
NYSERDA picked eight battery projects totaling 950 MW from 46 bids, using 15-year revenue guarantees to fix a storage market stuck at 80 MW of bulk capacity.

Waypoints
Eight battery projects totaling 950 MW won NYSERDA contracts, selected from 46 bids; New York targets 6 GW of storage by 2030.
As of March, New York had only 80 MW of operational bulk storage plus about 335 MW of small-scale batteries.
Contracts use a strike-price structure with 15 years of predictability: NYSERDA tops up projects when market revenue falls short and collects payments when projects overperform.
New York has awarded state contracts to eight grid battery projects that will collectively add 950 MW of non-emitting, on-demand capacity by 2030. The New York State Energy Research and Development Authority (NYSERDA) announced the winners last week, selecting eight projects from a field of 46 bids submitted in response to a solicitation released in July 2025.
The awards mark the state's largest intervention to date in a storage market that has barely materialized on its own. As of March, New York contained just 80 MW of operational bulk storage, plus roughly 335 MW of small-scale batteries — far short of the state's 1,500 MW target for 2025, though officials claimed success by counting awarded but not-yet-built projects.
The 950 MW of new contracts represent meaningful progress toward New York's goal of 6 GW of storage by 2030, a mandate the state sees as essential to eliminating fossil-fueled electricity by 2040. NYSERDA plans to run two more solicitations of this type to maintain momentum.
Why the market stalled
New York's weak battery track record is not for lack of policy effort. The state adopted its first formal storage target in 2018, but market dynamics in the statewide grid system failed to support development. The capacity market offers only six months of predictable revenue — a hard sell to financiers underwriting a 20-year battery investment. Utility procurement attempts over the years largely proved fruitless.
So the state stepped in. NYSERDA's 2022 Energy Storage Roadmap called for centralized procurement to jump-start progress. The plan won approval from the state's utility regulator in June 2024, the proposal call went out in July 2025, and the winners — including Flatiron Energy, Grid Connected Infrastructure, Key Capture Energy, Savion, and Zenobē — were named last week.
"To earn an award, proposers need to demonstrate that the project is competitively priced, is mature and viable, can provide electric system value, and spurs in-state economic activity," NYSERDA said in an email to Canary Media.
A contract structure built for ratepayer protection
The developers will not receive upfront cash. Instead, NYSERDA structured the deals to guarantee long-term revenue certainty. Each applicant submitted a strike price reflecting the revenue needed to make the project worth building. Once a battery enters the market, NYSERDA calculates a monthly reference rate based on real wholesale pricing in that project's zone of the grid.
"If the wholesale markets are lower than what the project needs, then NYSERDA tops us up," said Amit Barnir, vice president of network infrastructure at Zenobē, a U.K.-based storage developer that won a contract for a 100 MW battery in Burns, New York. "On the flip side of that, if we are generating more than what the project needs, we actually pay back NYSERDA."
NYSERDA says this two-way settlement protects ratepayers while pushing owners to bid competitively. Operators can also earn more by outperforming the zonal reference case, which gives them an incentive to maximize market participation through siting and trading strategy.
"You are settled on a zonal level, but the project earns revenues at a nodal level," Barnir said. "So picking the right node is critical for being successful in this program, from our perspective."
Zenobē, for instance, sited its battery next to a 100 MW solar plant under construction by AES. The solar project feeds the same substation the battery connects to, positioning Zenobē to charge on cheap midday solar and discharge into higher-priced peak hours.
Storage meets generation
NYSERDA announced 719 MW of renewable energy contracts alongside the battery selections, adding future clean generation for the new storage fleet to absorb.
The buildout should also pressure energy prices downward. In competitive markets, batteries undercut peaker plants by arbitraging electricity rather than burning fuel. New York City in particular still relies on decades-old fossil peakers that are expensive, inefficient, and polluting. A state environmental rule mandated shutting those plants down, but the city has struggled to build local battery capacity to replace them.
The core problem was never that batteries lacked value in New York — it was that existing market rules made them nearly impossible to finance. NYSERDA's plan addresses that directly with 15 years of revenue predictability and minimal outlay from ratepayers.
The next milestones to watch: NYSERDA's two follow-on solicitations, and whether the contracted 950 MW converts from announced awards into operational capacity ahead of the 2030 deadline for the state's 6 GW target.
via linkedin.com (Original)
More from Rebecca Stone
Show full bio
News editor covering consumer brands and retail at Circular Wire.
125 articles