New Zealand locks 2028 date for full battery trading in power market

New Zealand's Electricity Authority corrects the full-capacity battery trading date to March 31, 2028 and delays hybrid plant consultation to early 2027, citing software upgrade timelines.

New Zealand confirms 2028 rollout for battery market reforms
New Zealand confirms 2028 rollout for battery market reformsArtTower / pixabay

Waypoints

  1. Full-capacity battery trading starts March 31, 2028 under a corrected effective date

  2. Batteries get 10 price bands each for bids and offers, versus 5 for other generators

  3. Since Oct. 30, batteries must be dispatchable when charging, not only discharging

  4. Hybrid plant consultation moved from late 2026 to early 2027

  5. Four utility-scale batteries were connected to New Zealand's grid as of September

New Zealand's Electricity Authority Te Mana Hiko has set March 31, 2028 as the corrected effective date for full-capacity battery trading in the wholesale market, and pushed its consultation on battery-hybrid plant arrangements from late 2026 to early 2027.

The date correction matters more than it sounds. The regulator published the wrong effective date twice — once in its Sept. 29 decision paper and again in the subsequent amendment to the Electricity Industry Participation Code. Traders and plant developers who had pencilled in the earlier date now have a fixed anchor for planning software, bidding strategies and commissioning timelines.

What changes for battery owners?

From March 31, 2028, battery owners can trade their full capacity, with state-of-charge constraints built into the dispatch software to limit charging and discharging to feasible levels based on stored energy. The market design gives them:

  • Charging bids and discharging offers on a single trade form
  • A single dispatch instruction covering both directions
  • Up to 10 price bands for bids and 10 for offers — double the five-band maximum that applies to offers from other generators

That 10-band structure is the corrected rule the authority flagged this week: the September paperwork stated it but attached the wrong effective date.

Gate closure for batteries connected to local distribution networks also moves from 30 minutes to one hour, aligning them with batteries connected directly to the transmission grid. The authority deferred that change after industry feedback and pushed the final phase back three months to allow the System Operator to upgrade software for multiple frequency keeping — an ancillary service that maintains grid frequency.

Why the two-phase rollout?

The Sept. 29 decision implements the reforms in two phases because the required software upgrades take time. Phase one is already live: since Oct. 30, utility-scale batteries must be dispatchable when charging from the grid, not just when discharging.

"We consider they should be dispatchable across their full operational range as they are highly controllable assets," the authority said in its decision paper.

In the interim, battery owners can trade on expected capability and update offer and bid quantities after gate closure — the point at which bids and offers lock in before dispatch — if that capability changes. The regulator acknowledged the existing arrangements may encourage conservative trading, because a battery's ability to charge or discharge shifts quickly as its stored energy changes.

For prospective battery-hybrid plant owners, guidance on how to operate and trade in the market in the interim is coming shortly, the authority said.

A small fleet, growing fast

The September decision paper counted four utility-scale batteries connected to New Zealand's power system, with many more planned. The build-out is accelerating as the country's hydro-dominated system faces climate pressures on its generation mix. Contact Energy opened its Glenbrook battery south of Auckland in June, and French manufacturer Saft was selected in 2024 to supply a 200 MWh battery project in the country.

What to watch next

The near-term milestone is the interim guidance for hybrid plant owners, due shortly, followed by the market-arrangements consultation in early 2027. Whether the March 31, 2028 full-capacity date holds now depends on the System Operator's frequency-keeping software upgrade — the same dependency that already cost the schedule three months.

via pv-magazine-australia.com (Source)

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering technology and product news in Circular economy and the environmental industry at Circular Wire.

547 articles

Nearby routes

« Previous article