Edify Files for Federal Approval on 800 MW Queensland Solar-Battery Hybrid
Edify Energy has referred its 800 MW Glenatron solar farm and 800 MW, four-hour battery in Queensland's Darling Downs to federal EPBC assessment.

Waypoints
Glenarbon combines an 800 MW solar farm with an 800 MW, four-hour (3,200 MWh) battery on 1,500 hectares near Goondiwindi, Queensland.
Edify says the project will generate up to 1,555,000 MWh of dispatchable renewable energy per annum.
The site connects to the NEM via an existing Powerlink 330 kV transmission line crossing the project area.
Edify's Queensland projects Smoky Creek, Guthrie's Gap, Ganymirra and Majors Creek total 1,080 MWp solar and 900 MW / 3,600 MWh of DC-coupled BESS.
Edify, owned by Canada's La Caisse since a $1.1 billion takeover, holds federal approval for the 300 MW / 2,400 MWh Nowingi project in Victoria.
Edify Energy has referred its Glenarbon Solar Power Station — an 800 MW solar farm paired with an 800 MW, four-hour battery — to the federal government for assessment under the Environment Protection and Biodiversity Conservation (EPBC) Act, kickstarting the approval clock for one of Queensland's larger hybrid proposals.
The referral, now in the federal pipeline, places the project on a 1,500-hectare site roughly 65 kilometres east of Goondiwindi in the Darling Downs region, close to the New South Wales border. According to the documents filed for assessment, the facility would connect into the National Electricity Market through an existing Powerlink 330 kV transmission line that already crosses the project area.
That grid link matters. Building under an existing line removes one of the slowest, most contested steps in renewable project development: negotiating a new connection. The takeaway here is simple — Glenarbon's fate now rests on environmental assessment, not grid access.
What would the project actually deliver?
Edify puts the annual output figure at up to 1,555,000 MWh of dispatchable renewable energy per annum once the plant is operational. The four-hour battery gives the project 3,200 MWh of storage capacity, enough to shift solar generation into evening peak demand.
"The proposed BESS component will store excess energy generated by the solar farm and support the grid by providing power to the grid in peak periods of demand or when there is no lack of energy generation," the developer said in the referral, describing the battery's role in firming the solar output.
The site itself is far from pristine bushland. It has been largely cleared and is currently running as grazing country for sheep and cattle. Edify expects the project will not be deemed a controlled action under the EPBC Act, arguing any potential negative impacts can be handled through mitigation measures. In plain terms, the company is betting the federal environment department sees a lightly disturbed farming property, not a biodiversity battleground.
How does Glenarbon fit Edify's build-out?
Glenarbon is one entry in a portfolio that has grown substantially since Canadian investment group La Caisse bought Edify in a $1.1 billion takeover deal. Edify was an early mover in Australian batteries, building the country's first co-located battery at Gannawarra in Victoria — adjacent to, but separately connected from, a solar farm.
The current pipeline and operating fleet spans 17 solar projects and 16 batteries, either standalone or backing up PV. The Queensland cohort includes:
- Smoky Creek and Guthrie's Gap — twin solar and battery projects that reached financial close
- Ganymirra and Majors Creek — hybrid projects in far north Queensland, also at financial close
Together, those four Queensland projects supply 1,080 MWp of solar alongside 900 MW / 3,600 MWh of DC-coupled battery energy storage. Add Glenarbon's 800 MW solar and 3,200 MWh of storage, and the state's southwest emerges as a clear centre of gravity for the company.
Edify has also secured federal environmental approval for its Nowingi Solar Power Station in northwest Victoria, combining a 300 MW solar plant with a 300 MW / 2,400 MWh BESS — a useful precedent showing the company can clear the same EPBC hurdle Glenarbon now faces.
What happens next?
The decision point is the EPBC referral itself. If the federal environment department accepts Edify's argument and classes Glenarbon as not a controlled action, the project skips a full assessment and moves toward construction approvals at state level. If it is declared a controlled action, the timeline stretches through federal assessment before any concrete is poured.
Either way, the referral decision — not the technology, not the grid connection — is the milestone that sets Glenarbon's pace from here.
via pv-magazine-australia.com (Source)