NRC issued a draft FONSI for NuFuels' 20-year Crownpoint ISR uranium license and renewed the ACRS charter to 2028, as New Mexico and Diné groups challenge the project before a licensing board.

NRC Renews Reactor Safeguards Committee Charter and Issues Uranium Recovery Assessment
NRC Renews Reactor Safeguards Committee Charter and Issues Uranium Recovery AssessmentObelixlatino / pixabay

Waypoints

  1. NRC issued a draft FONSI on November 20, 2026 for a 20-year license renewal of the Crownpoint ISR uranium project (Docket NRC-2026-1882).

  2. Public comments on the draft environmental assessment close December 21, 2026.

  3. ACRS charter renewed through December 2, 2028 under Atomic Energy Act Section 29.

  4. License SUA-1580 was first approved in 1998; construction never began.

  5. Aquifer restoration to pre-operational baseline required under 10 CFR Part 40, Appendix A, Criterion 5B(5).

The Nuclear Regulatory Commission issued a draft Finding of No Significant Impact on November 20, 2026 for a proposed 20-year license renewal of the Crownpoint in-situ uranium recovery project in McKinley County, New Mexico — over the objections of state regulators and Navajo community groups. On the same day, the Commission renewed the charter of its independent reactor safety committee through December 2, 2028.

The two actions, both filed for public inspection on November 20, cover separate ends of the nuclear fuel cycle: fuel extraction licensing in New Mexico and statutory peer review for reactor safety nationwide.

What did the NRC decide?

Under Document 2026-23761, scheduled for Federal Register publication November 23 at 91 FR 75572, the NRC renewed the charter of the Advisory Committee on Reactor Safeguards (ACRS) through December 2, 2028. Federal Advisory Committee Management Officer Russell E. Chazell of the NRC Office of the Secretary in Rockville, Maryland, signed the renewal, which rests on Section 29 of the Atomic Energy Act of 1954 and the Federal Advisory Committee Act.

The committee — up to 15 independent technical specialists appointed by the Commission — reviews reactor operations, probabilistic risk assessment, thermal-hydraulic phenomena, materials degradation, and structural mechanics. In recent years its scope has widened to small modular reactors, advanced non-light-water designs, and the technology-neutral Part 53 licensing rule.

The second action is a Draft Environmental Assessment, draft FONSI, and draft Programmatic Agreement for Source and Byproduct Materials License SUA-1580 (91 FR 75356, Docket ID NRC-2026-1882). The applicant, NuFuels, Inc. — a subsidiary of Laramide Resources Ltd. — wants a 20-year license renewal to construct and operate an ISR project at Church Rock Sections 8 and 17, Unit 1, and Crownpoint.

How would extraction work, and what's the restoration bar?

NuFuels plans to recover uranium from deep sandstone aquifers in the Westwater Canyon Member of the Morrison Formation. Oxygenated alkaline lixiviant would circulate through injection wells, dissolve uranium minerals, and return them to the surface for ion-exchange recovery.

The binding cleanup obligation sits in 10 CFR Part 40, Appendix A, Criterion 5B(5): before decommissioning, NuFuels must restore affected groundwater to pre-operational background quality or approved secondary standards. That restoration baseline is the technical heart of the state's pushback.

Who is fighting the project?

The site carries heavy history. The NRC first approved License SUA-1580 in 1998, but construction never started, blocked by market shifts and sustained litigation. The 1979 Church Rock tailings spill contaminated the Puerco River, and in 2005 the Navajo Nation enacted the Diné Natural Resources Protection Act banning all uranium mining and processing within Navajo Indian Country.

New Mexico, through the Environment Department (NMED) and the Department of Justice, has intervened to challenge the renewal. NMED Cabinet Secretary James C. Kenney emphasized the state must protect regional drinking water supplies, flagging potential communication between the ore zone and aquifers serving the City of Gallup.

Diné community members, represented by the New Mexico Environmental Law Center, voiced opposition at public meetings and demanded full cleanup of legacy tailings before any new ISR mining proceeds. NRC staff, by contrast, concluded that NuFuels' monitoring wells, excursion recovery plans, and surety bonding satisfy safety regulations. Laramide Resources commended the draft FONSI, saying ISR produces minimal surface disturbance while supplying domestic uranium feedstock.

Why does the ACRS renewal matter?

Congress created the ACRS in 1953 and made it a statutory body in 1957. Section 182b of the Atomic Energy Act requires the committee to independently review construction permits and operating licenses for commercial power reactors and major testing facilities.

That mandate reaches university research and test reactors too — TRIGA and pool-type facilities fall under ACRS review for license renewals, power uprates, and digital instrumentation upgrades. The Crownpoint docket, meanwhile, gives hydrogeologists empirical data on groundwater transport and aquifer restoration timelines under 10 CFR Part 40.

What happens next?

  • December 2, 2026 — renewed ACRS charter takes effect, authorizing committee meetings through December 2, 2028.
  • December 21, 2026 — the 30-day public comment window on the draft EA and Programmatic Agreement closes.
  • Early 2027 — the Atomic Safety and Licensing Board hears arguments on intervention petitions from New Mexico, NMED, and tribal groups.
  • Mid-2027 — NRC staff decides whether to finalize the FONSI or order a full Environmental Impact Statement.
  • 2027–2028 — ACRS holds monthly meetings on SMR licensing, fuel qualification, and Part 53.

The mid-2027 FONSI-or-EIS decision is the milestone that settles whether this license renewal finally moves to construction — or reverts to the litigation track that has stalled it since 1998.

via casrai.org (Source)

Share this article:

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering technology and product news in Circular economy and the environmental industry at Circular Wire.

575 articles

Nearby routes

« Previous article