TSL quits £5.2bn Agratas gigafactory build, second exit in five months
TSL has quit the £5.2bn Agratas gigafactory at Bridgwater, leaving the UK's flagship EV battery plant without a main contractor after a second exit in five months.

Waypoints
Agratas lost main contractor TSL, its second lead builder exit in five months after sacking Sir Robert McAlpine in June.
The Bridgwater, Somerset gigafactory is valued at £5.2bn and carries a £380m UK government pledge, not all of it paid out.
Production start moved from 2026 to 2027; the current target is January 2028 with up to 4,200 jobs planned.
TSL expects to leave the site within two or three months, and no replacement main contractor is appointed.
JLR has secured cells from other suppliers, so its electric Land Rover and Jaguar sales plans are unaffected.
TSL has walked away from the £5.2bn Agratas battery gigafactory at Bridgwater, Somerset, leaving Britain's flagship electric vehicle battery project without a main build contractor for the second time in five months.
Agratas and Jaguar Land Rover, its customer, both belong to the Tata Group. The UK government has pledged £380m in support for the factory, viewing it as crucial to the long-term survival of the British car industry, though not all of that money has been paid out.
Agratas did not respond to a request for comment on the contractor's exit; TSL and JLR declined to comment. NG Bailey, the project's mechanical, electrical and plumbing contractor, was approached for comment.
Why did the main contractor leave?
The dispute centres on the timeline and cost of the build, according to two sources. TSL, formally known as Tonroe Group, expects to leave the site within two or three months, and no replacement main build contractor is in place. NG Bailey could yet step up to run the entire construction.
Agratas has not formally moved its latest start-of-production date of January 2028. A company spokesperson said: "We are on track to meet our customer requirements. The Somerset site is a large and complex industrialisation project, and all of our supplier partners are supporting us well as we prepare for the facility's launch phase."
How far behind schedule is the project?
The plant was announced in 2023 with a target of 2026 for the start of production and as many as 4,200 employees. Tata then pushed the start to 2027, and the current date of January 2028 now depends on finding a new lead builder.
- 2023: Tata announces the Bridgwater gigafactory
- 2026: original start-of-production target
- June: Agratas fires lead contractor Sir Robert McAlpine at short notice, with departure terms still under discussion
- 2027: production start pushed back
- January 2028: current target, with no main contractor appointed
What is already standing at the site?
The shell of the building is mostly complete in south west England, and National Grid has started work on the electricity substation that will supply the heavy power loads a cell plant needs. Agratas has also made progress at a second site in Sanand, western India. Some Agratas managers travelled to India this week to share experience with their counterparts there and discuss the UK situation.
Does this stall Jaguar Land Rover?
No, at least not on vehicle sales. JLR has secured batteries from other suppliers, so its plans to increase sales of new electric Land Rovers and Jaguars stand. Those first cars will not carry British-made cells, though the manufacturer could also avoid EU tariffs under "rules of origin" by using batteries made in Europe.
How does Somerset compare with rival UK plants?
AESC's plant in Sunderland, north-east England, remains the UK's only operating gigafactory, but it has also struggled as carmakers scale back electric vehicle plans and governments delay bans on petrol and diesel cars. The Guardian reported in August that AESC shelved expansion after failing to agree a separate deal to supply JLR.
Global battery supply remains dominated by China, South Korea and Japan. Successive Conservative and Labour governments have backed a domestic supply chain, a policy that also fits Andy Burnham's hopes to "reindustrialise" the UK.
An earlier rival, Britishvolt, collapsed after failing to secure firm orders. Its former north-east England site is now being turned into a datacentre for artificial intelligence, an attractive prospect for an empty building with a high-capacity grid connection.
What decides what happens next?
The immediate milestone is a replacement main contractor. Agratas also faces internal strain after deciding to relocate some workers from a Coventry building shared with other Tata companies to Somerset, some 120 miles away. Some of those workers are expected to take redundancy rather than uproot their families, extending a run of senior departures, two sources said.
If Agratas cannot appoint a builder and hold January 2028, the Somerset site risks Britishvolt's fate, and the unspent share of the government's £380m pledge comes under sharper scrutiny.