DOE Dockets Hill County Electric's 6-to-8 MW Canada Export Amendment
DOE docketed Hill County Electric's request to lift cross-border export capacity from 6 MW to 8 MW for Enbridge's Wildhorse pump station in Alberta. Comments close December 30, 2026.

Waypoints
Docket EA-118-A, accepted November 27, 2026, would raise authorized export capacity from 6 MW to 8 MW across a 69-kV line from Montana to Alberta.
The power feeds Enbridge's Express Pipeline Wildhorse pumping station, supporting potential crude throughput expansion.
The 2 MW addition sits below the Upper Missouri Zone's 4 MW unplanned-load threshold, exempting HCE from balancing authority pre-authorization.
The underlying authorization dates to February 6, 1997 (Order EA-118, Presidential Permit PP-118).
Public comments and interventions are due December 30, 2026.
A 2-megawatt increase in authorized cross-border electric exports is now on the federal docket. On November 27, 2026, the US Department of Energy's Office of Electricity accepted Hill County Electric Cooperative's application to lift its permitted export capacity from 6 MW to an instantaneous 8 MW across the Montana-Canada border, under Docket No. EA-118-A (Federal Register Doc. 2026-24273).
The application amends an authorization originally granted on February 6, 1997, under Order No. EA-118 and Presidential Permit PP-118. Hill County Electric (HCE), a distribution cooperative based in Havre, Montana, filed its first amendment request on August 20, 2026, and a revised submission on September 30, 2026.
What's the power actually for?
The 69-kilovolt line is a radial cross-border feeder delivering electricity to the Wildhorse pumping station in Alberta, operated by Express Pipeline Ltd., a subsidiary of Enbridge Inc. Enbridge requested the capacity increase to support potential throughput expansion along the Express Pipeline system, which moves Canadian crude directly into US refining markets.
So the electrons flowing south of the border are, functionally, pipeline horsepower. A 2 MW bump is small by bulk-transmission standards — interregional ties run at 230 kV or 500 kV — but for a dedicated radial line feeding industrial pumping load in rural northern Montana, where feeders span long distances with limited alternate routing, it's a material change.
Why the 2 MW stays under the reliability screen
Under Section 202(e) of the Federal Power Act (16 U.S.C. 824a(e)), DOE must find the export won't impair domestic supply or impede coordinated grid use. HCE's engineering load flow analysis concluded the increase falls well within its existing system capability and won't affect service to native Montana load.
The filing also clears the Upper Missouri Zone (UMZ) Zonal Planning Criteria: load growth above 4 MW counts as unplanned load requiring balancing authority approval. Because HCE's proposed 2 MW sits below that 4 MW threshold, it's classified as planned load growth — no separate balancing authority pre-authorization needed before federal review. HCE confirmed 8-MW operation won't disrupt bulk power network coordination or reduce availability to domestic customers, and DOE conditions keep exports interruptible during domestic grid emergencies, preserving retail service priority.
Who signed, and under what authority
Export jurisdiction moved from the Federal Power Commission to the Secretary of Energy under the DOE Organization Act (42 U.S.C. 7151(b), 7172(f)), with rules at 10 CFR Part 205. Under Redelegation Order No. S3-DEL-OE1-2026, executed January 8, 2026, the Secretary delegated authorization power to the Assistant Secretary for the Office of Electricity. Catherine Jereza, Assistant Secretary for the Office of Electricity, signed the notice on November 24, 2026; Alternate Federal Register Liaison Officer Jennifer Hartzell authorized electronic filing on November 25.
What happens next
The notice hits the Federal Register on November 30, 2026, opening a 30-day public comment and intervention window that closes December 30, 2026. Comments and intervention petitions go electronically to the DOE, marked with OE Docket No. EA-118-A, and will be posted to DOE's pending applications site. After the window closes, the Office of Electricity finalizes its NEPA review — under 10 CFR Part 1021 and DOE's June 2026 Implementing Procedures — and its grid reliability evaluation before issuing a final determination.
For practitioners tracking the precedent: this docket shows how a sub-4-MW export addition routes straight to federal review without balancing authority signoff, and how pipeline-driven load growth on radial cross-border feeders gets tested against FPA reliability ceilings. The comment deadline of December 30, 2026, is the date that decides what happens next.
via casrai.org (Source)
Filed underCross Border Electricity ExportsDepartment Of EnergyHill County ElectricFederal Power ActGrid Reliability