EIA Proposes First Federal Facility-Level Data Center Energy Survey

EIA proposes Form EIA-872, the first federal facility-level data center energy survey, mandating annual reporting from sites with at least 1 MW of IT design capacity starting in 2027.

Energy Information Administration Opens Comment on Federal Energy Statistical Survey Collections
Energy Information Administration Opens Comment on Federal Energy Statistical Survey CollectionsMichael_Pointner / pixabay

Waypoints

  1. Form EIA-872 requires annual reporting from data centers with at least 1 MW IT design capacity, starting 2027 for the 2026 reference year.

  2. Domestic data centers consumed an estimated 176-192 TWh in 2023-2024, roughly 4.4-4.7 percent of U.S. electricity, per DOE estimates.

  3. Comments on Federal Register Document 2026-24077 close January 26, 2027, with an estimated 12,200-hour industry reporting burden.

  4. EIA projects data centers could reach nearly 12 percent of U.S. electricity consumption by 2030.

The U.S. Energy Information Administration has proposed the first federal statistical survey to collect facility-level energy consumption data from large data centers, with mandatory annual reporting from any site holding at least 1 megawatt of IT design capacity. The proposed Form EIA-872, the Data Center Energy Consumption Survey, would begin collecting data in 2027 for the 2026 reference year.

EIA placed Federal Register Document 2026-24077 on public inspection on November 26, 2026, ahead of scheduled publication on November 27, 2026. Pushpal Mukhopadhyay, Director of the EIA Office of Statistical Methods and Research, signed the notice in Washington, D.C., on November 23, 2026. The agency requests Office of Management and Budget approval under statutory authorities at 15 U.S.C. 772(b) and 42 U.S.C. 7101.

What does the survey cover?

The reporting obligation falls on a broad set of facility categories. Covered sites include:

  • Enterprise data centers
  • Commercial colocation facilities
  • Hyperscale cloud centers
  • Edge computing hubs
  • Carrier hotels and network gateways
  • Cryptocurrency mining sites
  • Emerging super intelligence (SI) artificial intelligence computing clusters

The survey defines a data center facility as a dedicated building, multiple buildings, or a delineated portion of a structure whose primary purpose is housing servers, storage, and networking hardware. Functionally integrated multi-building campuses that share common power delivery or cooling infrastructure count as unified reporting units. Facilities below the 1 MW design threshold fall entirely outside the scope.

EIA explicitly stated that it is not proposing to collect confidential business information about commercial customers or computing tenants. All reported data will be protected under the Confidential Information Protection and Statistical Efficiency Act of 2018, meaning individual responses cannot be disclosed in identifiable form and may appear only in aggregate statistical summaries.

Why is EIA replacing CBECS?

The federal government has never collected uniform, facility-level end-use power metrics from large computing installations. The existing Commercial Buildings Energy Consumption Survey, a sample-based collection last run for the 2018 reference cycle, cannot capture modern computational facilities, according to EIA.

The agency found that data centers exceed standard office buildings in power density by orders of magnitude. They also rely on continuous baseline electrical draws, complex uninterruptible power supply arrays, and sophisticated air- or liquid-cooling infrastructure that real estate surveys miss.

The gap has widened as artificial intelligence workloads accelerate grid demand. DOE assessments, supported by Lawrence Berkeley National Laboratory research, estimated domestic data centers consumed roughly 176 to 192 terawatt-hours of electricity in 2023 and 2024, or about 4.4 to 4.7 percent of total national electricity consumption. Projections suggest that share could approach 12 percent by 2030.

How are analysts reacting?

Researchers Molly Robertson and Karen Palmer, in a Resources for the Future study titled The Hype on Hyperscalers: Data Centers and Growing Electricity Demand, flagged extreme uncertainty in power growth forecasts. They observed that data centers can be built in two to three years, while transmission lines and clean energy generation assets require five to ten years. That planning friction has pushed utilities toward specialized clean transition tariffs to shield residential ratepayers from infrastructure upgrade costs.

Mukhopadhyay said Form EIA-872 forms part of a broader agency drive to move consumption surveys from multi-year intervals to an annual cadence, with empirical reporting replacing speculative estimation models that dominate current discussion of AI energy use.

What does the change mean for institutions?

University high-performance computing centers, national laboratories, and shared user facilities frequently exceed the 1 MW threshold, while most campus server rooms sit below it. Research offices must determine whether partitioned institutional facilities report directly or fall under broader campus classifications. Compliance officers face an estimated 12,200-hour aggregate reporting burden across the industry. The dataset itself will give energy economists and grid modelers a verifiable baseline, replacing bottom-up estimates built from server shipment data.

What happens next?

The notice opens a 60-day public comment window under the Paperwork Reduction Act, with comments due on or before January 26, 2027. EIA seeks input on five points: practical utility, the accuracy of the 12,200-hour burden estimate, data quality improvements, burden reduction through automated submission, and the technical soundness of the 1 MW threshold and the facility definition. Comments identified by Form EIA-872 go to EIA Clearance Officer Maura Bardos Chihil. After the comment period closes, EIA will revise the instrument and submit a formal Information Collection Request to OMB for final clearance ahead of 2027 deployment.

via casrai.org (Source)

More from Rebecca Stone

Rebecca Stone

Show full bio

News editor covering companies, deals and strategy in Circular economy and the environmental industry at Circular Wire.

574 articles

Nearby routes

« Previous articleNext article »