Industrial Decarbonization
Nine Australian Data Centre Projects Could Add 39.7 Million Tonnes of Emissions
Nine Australian data centre proposals could add 39.7 million tonnes of annual emissions by 2035 — near the output of Loy Yang A, Eraring and Bayswater combined — without new renewables and storage.

Waypoints
Nine Australian data centre proposals could add 39.7 million tonnes of climate pollution annually by 2035 without new renewables and storage.
Projected emissions approach those of the three dirtiest coal plants combined: Loy Yang A, Eraring and Bayswater.
Data centres could lift wholesale power prices 20 percent across the main grid by 2035 without matching new supply.
Three developers, some tied to the gas industry, propose gas stations larger than any operating in Australia today.
Reported standards demands: 30 MW facilities must match demand with new renewables and storage within three years; gas excluded as primary power.
Australia's nine most polluting data centre proposals could add 39.7 million tonnes of climate pollution a year by 2035 unless developers bring new solar, wind and storage to match their demand. That is the central finding of a new analysis by the Climate Council and the Carbon Zero Initiative, published under the title Pollution Pipeline: Australia's Dirtiest Data Centres.
The scale deserves a number for comparison. The projected annual emissions from these nine projects approach the combined output of the country's three dirtiest coal power stations: Loy Yang A, Eraring and Bayswater. Australia's digital infrastructure build-out, in other words, risks recreating the emissions profile of the coal fleet it is meant to supersede.
The finding lands at a moment of unusual acceleration. Data centre development in Australia has moved from speculative land deals to grid connection queues, and the analysis suggests the electricity sector has not yet priced what that means. The material consequence is straightforward: demand growth without matching supply is a cost passed to every other user of the grid.
What does the analysis actually claim?
The report makes three further findings, each anchored to the national electricity market:
- Three developers, some with ties to the gas industry, want to build gas power stations larger than any currently operating in Australia.
- Without new renewables and storage, data centres could push wholesale power prices up 20 percent across the main grid by 2035.
- Gas-fired data centres would tighten gas supply for Australian industries that need it, undermining the proposed Domestic Gas Reservation Scheme.
That third point is the quiet one worth watching. The Domestic Gas Reservation Scheme exists precisely to secure supply for domestic industrial users. Siting a new class of gas-hungry load beside it creates a direct policy contradiction.
The gas dimension matters for another reason. The three proposed gas stations would not be marginal additions. They would exceed the capacity of anything running in Australia today, which means new infrastructure, new supply contracts and new emissions locked in for decades. A data centre built in 2026 and fuelled by gas is a commitment with a 2050 expiry date nobody has signed for.
What do the authors want the government to do?
The Climate Council and Carbon Zero Initiative argue these outcomes are not inevitable. They call on the Albanese Government to close what they describe as loopholes in its promised national standards. At minimum, the organisations say, the standards should:
- Require every facility over 30 MW — including projects already in the pipeline — to match its demand with new renewables and storage built within three years;
- Rule out gas as a primary power source; and
- Place strict limits on water use, including no fresh water for cooling in water-stressed regions.
Each of those three demands carries a deadline logic. The 30 MW threshold catches the facilities that matter; the three-year matching requirement converts pledges into dated commitments; the water limits address a resource constraint that sits outside the electricity debate but follows the same siting decisions.
The treatment of existing pipeline projects is the sharpest edge. Standards that apply only to new applications would exempt most of the problem, because the nine proposals at the centre of this analysis already exist on paper. The report's authors are explicit that retrofitting obligations to in-flight projects is the point, not an afterthought.
Can the proposals be tracked?
The Climate Council has launched a public tracker, the Dirty Data Centre Watch, listing the most polluting data centre proposals. It will be updated as new projects are announced or as existing proponents commit to building enough renewable energy and storage to match their demand. That mechanism turns a one-off report into a standing scorecard, and it gives every pledge a place to be tested.
What decides what happens next?
The decision now sits with the Albanese Government's national standards, which are promised but not yet finalised. Whether they apply to facilities over 30 MW already in the pipeline, and whether gas is excluded as a primary power source, will determine whether the 39.7 million tonne figure becomes a forecast or a footnote. The standards are the milestone; everything else is commentary.
via azocleantech.com (Source)
More from Olivia Hart
Show full bio
Staff writer covering regulation, policy and their impact on Circular economy and the environmental industry at Circular Wire.
550 articles