Up to 177 GW of Behind-the-Meter Gas Queued for US Data Centers
Proposed behind-the-meter gas for US data centers has reached 90–177 GW, doubled in six months. NRDC warns of a 10% rise in power sector emissions and $14.4 billion in added gas costs by 2030.

Waypoints
90–177 GW of behind-the-meter gas projects are proposed for US data centers; the count doubled in H1 2026.
Full build-out would raise US power sector emissions by 10 percent, per Bloomberg New Energy Finance.
Amazon's Pecos, Texas project is approved to emit 33 million tons of CO2, the largest single US source.
Data center gas demand could raise natural gas prices 5.8–15.9 percent by 2030, costing customers $14.4 billion.
A McKinsey survey found 60 percent of developers expect on-site gas to be permanent, not a bridge.
Between 90 and 177 gigawatts of behind-the-meter gas generation is now proposed for US data centers, after the number of projects doubled in the first half of 2026 alone. The NRDC analysis behind those figures estimates that building every proposed plant would raise US power sector emissions by 10 percent, citing Bloomberg New Energy Finance.
The scale is not abstract. Run at 90 percent of capacity, that capacity would generate as much electricity as 68 million to 133 million average households consume in a year. Data centers could reach 649 terawatt-hours of annual consumption by 2030, more than a tenth of all US electricity use.
Why developers are going behind the meter
Grid interconnection queues, slow long before the data center boom, now stretch five to seven years in some regions. Building generation on-site, independent of the grid, buys speed in a sector that prizes it above cost. Most facilities still take supplemental grid power for 24/7 supply rather than running fully islanded, though islanded proposals are multiplying.
Behind-the-meter gas is more polluting than full grid supply even where the grid itself burns a lot of gas. Combined-cycle plants are more efficient and better regulated than the reciprocating engines and repurposed jet engines favored on-site. Demand for the most efficient large methane turbines has pushed new order deliveries to at least 2031, so developers turn to smaller, dirtier hardware instead.
A McKinsey & Company survey of data center developers found 60 percent of respondents expect permanent on-site gas even after a grid connection becomes available. The bridge, in other words, is built to last.
Permitting games and stalled projects
The analysis documents developers exploiting a patchwork of regulation: strapping engines to trucks to qualify as mobile sources, and splitting BTM resources into multiple smaller permit applications. Others, the NRDC writes, have allegedly ignored regulatory requirements entirely. Operating illegally may expedite operations, but it is not a viable strategy. Also, it is illegal.
Speculation runs high regardless. Many proposed projects lack permits, a large share lack a secured turbine supplier, and construction is stalling on local opposition, material shortages, and labor constraints.
The named projects and their numbers
- Pecos, Texas. Amazon plans a 7.65 GW off-grid data center with 35 on-site gas turbines. State approvals permit 33 million tons of CO2 emissions, which would make it the single-largest source of CO2 in the United States.
- Rio Grande Valley, Texas. A permit was issued for Elon Musk's proposed $24 billion data center: 35 natural gas turbines producing 750 MW.
- Utah. The proposed 9 GW Stratos data center could emit 3,140 tons of PM2.5 per year, an NRDC-commissioned analysis found, drifting into Colorado, Idaho, and Wyoming and causing 45 additional premature deaths and $690 million in annual health damages.
Who pays
An MIT study found data centers connecting to the grid drove average retail electricity prices up 2.7 percent from 2010 to 2024; for investor-owned utilities serving about two-thirds of Americans, prices rose 5.6 percent. Going off-grid does not spare consumers. Evolved Energy Research projects data center gas demand will raise natural gas prices 5.8 to 15.9 percent nationally by 2030, costing customers an additional $14.4 billion.
The EPA has attempted to repeal and weaken bedrock regulations and has exempted some off-grid data centers from certain requirements, which the NRDC argues makes gas generators easier to build and harder to litigate.
What happens next
With federal backstops eroding, the NRDC assigns responsibility to states and localities. Its recommendations include ending automatic and fast-tracked approvals, closing loopholes that let BTM projects bypass utility commission oversight and environmental review, eliminating by-right zoning, mandating disclosure of BTM build-out, and requiring setback, emissions, and noise limits plus cumulative impact assessments and community engagement.
Some jurisdictions are already moving: the proposed POWER Act in Illinois, and executive actions from Governors Abigail Spanberger in Virginia, JB Pritzker in Illinois, and Josh Shapiro in Pennsylvania.
The decisive variable, per the analysis, is whether the proposed BTM pipeline gets built, downsized, or canceled. Permitting and siting decisions made this year will settle which.