NRC Dockets Third Notice for Holtec's 680 MWe Palisades SMR Pair
NRC's third statutory notice covers Part 2 of Holtec's phased permit for two 300 MWe SMR-300 Pioneer units at Palisades, with a 60-day intervention window to follow docketing.

Waypoints
Two 300 MWe SMR-300 Pioneer units, ~680 MWe net total, filed under Docket Nos. 50-616 and 50-617.
Part 2 tendered September 30, 2026; third weekly notice published November 23, 2026.
DOE conditional loan guarantee of up to $1.52 billion backs the existing 800 MW unit restart.
Fourth statutory notice due early December 2026; 60-day intervention window follows docketing under 10 CFR 2.309.
Part 1 filed December 31, 2025 with Environmental Report and Limited Work Authorization request.
Two 300-megawatt-electric small modular reactors moved a step closer to formal NRC review on November 23, 2026, when the regulator published its third consecutive statutory notice of receipt for Part 2 of Holtec's phased construction permit application at the Palisades Energy Center in Covert, Michigan.
The notice, issued by the Office of Nuclear Reactor Regulation under Section 182a of the Atomic Energy Act of 1954, formalizes public availability of the application tendered by SMR, LLC on behalf of Palisades SMR, LLC, a wholly owned subsidiary of Holtec International. The filing is documented in Federal Register Document 2026-23826 under Docket Numbers 50-616 and 50-617 and covers Pioneer Unit 1 and Pioneer Unit 2, a dual-unit SMR-300 project with roughly 680 megawatts-electric of combined net capacity.
If licensed, the Pioneer units would supply baseload power to the regional grid and establish a commercial reference facility for modular light-water reactors. The verdict on that promise now rests with the NRC's acceptance review, not with the applicant.
What does the filing actually contain?
SMR, LLC filed Part 2 on September 30, 2026; it is accessible under NRC ADAMS Accession Number ML26273A416. The phased procedure under 10 CFR 2.101(a)(9) and 10 CFR 2.600(d) splits a construction permit application into two parts:
- Part 1, tendered December 31, 2025: an Environmental Report, three exemption requests, and a Limited Work Authorization (LWA) request under 10 CFR 50.10(d).
- Part 2, tendered September 30, 2026: the complete Preliminary Safety Analysis Report, an updated Quality Assurance Topical Report, and specific exemption requests under 10 CFR Part 50, incorporating Part 1 financial information by reference.
Weekly public notices began November 10, 2026, and will run four consecutive weeks — November 10, 17, 24, and December 1 — as required by 10 CFR 50.43(a)(3). Public records sit under Docket ID NRC-2026-0265 on Regulations.gov. In parallel, the NRC has approved an early site exemption permitting preliminary excavation, diaphragm cutoff wall construction, and dewatering before formal LWA issuance.
How does the design and money stack up?
The SMR-300 is a pressurized water reactor with an integral passive safety design. It relies on passive systems and natural circulation cooling, eliminating active emergency pumps, and places the reactor vessel in an underground containment structure built to mitigate external hazards. Validating those passive safety margins required extensive thermal-hydraulic and computational modeling, supported by national laboratories through a cooperative research and development agreement and federal cost-sharing awards.
The federal balance sheet is not trivial. The DOE Loan Programs Office has extended a conditional loan guarantee of up to $1.52 billion for the existing 800-megawatt unit, which operated from 1971 until shutdown in May 2022. Holtec bought the plant to decommission it; demand for clean industrial power reversed that plan, and the DOE Office of Nuclear Energy now supports the modular systems under its Advanced Small Modular Reactors research programs.
Michelle Hayes, Chief of Advanced Reactor Licensing Branch 2 in the NRC Division of Advanced Reactor Licensing, confirmed that the weekly notices provide public transparency during the acceptance review phase. Holtec International stated that completing Part 2 positions the Pioneer units among the most advanced commercial SMR applications undergoing 10 CFR Part 50 review in the United States.
Michigan state officials and regional energy coalitions back the project as support for clean-energy portfolio standards and skilled employment in Van Buren County. Local labor councils praised the expansion. Regional environmental groups plan to examine Lake Michigan water intake and spent-fuel storage during public hearings once formal petitions open.
What happens next?
The near-term calendar is fixed. The NRC publishes its fourth and final weekly notice in early December 2026. Project managers Michael Orenak, Victoria Huckabay, and Jason Lising will conclude the acceptance review to decide whether Part 2 is complete for formal docketing. If accepted, the NRC will publish a docketing notice opening a 60-day window for stakeholders to petition for leave to intervene under 10 CFR 2.309.
The agency will then issue a schedule for the Safety Evaluation Report and Environmental Impact Statement, coordinating with the U.S. Army Corps of Engineers and state authorities. Site preparation continues under active exemptions while the LWA and full construction permits remain pending.
The milestone that decides everything is the docketing decision, followed by the 60-day intervention window in early 2027.