FERC Sets February 2027 EA Deadline for 24.8 Bcf Texas Gas Storage Expansion
FERC scheduled a February 26, 2027 Environmental Assessment for Tres Palacios's 24.8 Bcf salt cavern conversion in Texas, with all federal permits due within 90 days under Docket CP26-556-000.

Waypoints
Tres Palacios Smith Cavern project adds 24.8 Bcf working gas storage; aggregate volume 33.73 Bcf in the Markham Salt Dome.
FERC's Environmental Assessment is due February 26, 2027; all federal authorizations must conclude by May 27, 2027 (90-day rule, 18 CFR 157.22(a)).
Project includes 5.4 miles of 36-inch pipeline loop and 38,500 hp of reciprocating compression across two stations.
Application filed July 22, 2026 by Tres Palacios Gas Storage LLC under Docket No. CP26-556-000.
EPA Region 6 raised NPDES/Clean Water Act and groundwater displacement issues during scoping that closed in fall 2026.
FERC has locked the environmental review clock for the Tres Palacios Smith Cavern Expansion Project: an Environmental Assessment due February 26, 2027, and a binding 90-day window that forces every other federal and state authorization to land by May 27, 2027.
The schedule notice, issued November 24, 2026, under Docket No. CP26-556-000, covers a project that would add 24.8 Bcf of working natural gas storage capacity in Matagorda and Wharton Counties, Texas, by 2027. Tres Palacios Gas Storage LLC filed the underlying application on July 22, 2026, seeking a Section 7(c) certificate under the Natural Gas Act to build, convert and operate the storage facilities. The notice was published in the Federal Register (91 FR 75851, Document No. 2026-23835) and issued by Commission Secretary Debbie-Anne A. Reese.
What gets built?
The project converts three existing subterranean brine caverns — Smith Caverns 5, 6 and 7 — into high-deliverability gas storage reservoirs within the Markham Salt Dome formation. The numbers:
- 24.8 Bcf of working gas capacity
- 8.93 Bcf of base gas, for an aggregate volume of about 33.73 Bcf
- 5.4 miles of new 36-inch-diameter pipeline loop
- Three 1.7-mile, 16-inch-diameter cavern laterals
Compression expands across two sites. The greenfield El Campo Compressor Station gets four 5,500 hp reciprocating units totaling 22,000 hp. Brownfield additions at the existing station add three more 5,500 hp units totaling 16,500 hp, plus a new compressor building, six cooling bays and a dehydration system. That's 38,500 hp of reciprocating compression in total. Three existing metering and regulation stations get retrofitted at header interconnections.
The takeaway: this is a conversion project, not a greenfield cavern dig — existing salt voids become pressurized storage vessels.
Why salt caverns matter to the market
Salt dome caverns are the fast-cycling end of the North American storage fleet. Unlike depleted reservoirs or aquifers, domal salt can cycle inventory multiple times a year and deliver peak withdrawal in fractions of an hour. The Gulf Coast location puts the facility at the intersection of LNG export demand and the ERCOT grid, where quick-start gas generation increasingly balances renewables. The Environmental Assessment carries NEPA tracking number EAXX-019-20-000-1790772608.
In plain terms: fast storage near LNG terminals and a renewables-heavy grid is exactly where traders expect volatility to be absorbed.
What did the scoping record raise?
FERC opened interagency scoping on September 22, 2026, after its initial Notice of Application on July 31, 2026. The record drew substantive comments from EPA Region 6 and citizen intervenors. EPA engineers flagged surface water protection, NPDES permit coverage under Clean Water Act Section 402, and potential displacement of deep groundwater aquifers during pipeline trenching and brine displacement — groundwater containment integrity is a primary review criterion when saturated brine gets hydraulically displaced during conversion.
Intervenors raised coastal prairie ecosystem disturbance, wetland hydrology, noise from the combined 38,500 hp of compressors, and cumulative NOx and greenhouse gas emissions. Commission staff stated in the procedural notice that all substantive scoping issues will be comprehensively evaluated in the EA.
What happens next?
The EA release on February 26, 2027 opens a formal public comment window. Once it closes, coordinating agencies must issue their permits by May 27, 2027 to satisfy the 18 CFR 157.22(a) mandate. After the environmental record closes, the five-member Commission deliberates on a Certificate of Public Convenience and Necessity. Filings and intervenor motions are trackable via FERC eSubscription under Docket No. CP26-556-000.
The May 27, 2027 permit deadline is the milestone that decides whether this 24.8 Bcf reaches service on schedule.