FERC sets 2027 review for Southern Star’s McNew pipeline

FERC scheduled the Evergy McNew gas pipeline environmental assessment for June 7, 2027, with a Sept. 5 federal deadline for the 123,000 MMcf/d Kansas proposal.

FERC Sets Environmental Assessment Schedule for Southern Star Evergy McNew Pipeline Project
FERC Sets Environmental Assessment Schedule for Southern Star Evergy McNew Pipeline Projectdamienboutin / pixabay

Waypoints

  1. FERC scheduled the environmental assessment for June 7, 2027, followed by a 30-day public comment period.

  2. Sept. 5, 2027 is the binding 90-day federal authorization deadline under 18 CFR 157.22(a).

  3. The proposal would transport up to 123,000 MMcf/d of firm natural gas to Evergy’s planned McNew plant.

  4. The proposed $1 billion combined-cycle plant is designed for 705 to 765 MW.

  5. The filing includes a 1.6-mile, 30-inch lateral and new compression and metering across three Kansas counties.

FERC will release the environmental assessment for Southern Star Central Gas Pipeline’s 123,000 MMcf/d Evergy McNew Delivery Project on June 7, 2027, setting a binding Sept. 5, 2027 deadline for federal and delegated state authorizations tied to the Kansas natural-gas proposal.

FERC published the schedule Nov. 24, 2026, in Federal Register Document No. 2026-23894 (91 FR 75850), under Docket No. CP26-572-000. Southern Star filed Aug. 31, 2026, for a Certificate of Public Convenience and Necessity under Section 7(c) of the Natural Gas Act, 15 U.S.C. 717f(c). FERC’s Notice of Application followed Sept. 15, starting federal coordination for the interstate line.

What does FERC’s schedule decide?

FERC staff plan to prepare an environmental assessment under the National Environmental Policy Act, tracked as EAXX-019-20-000-1788525221. The June 7 release opens an immediate 30-day public comment period for agencies and stakeholders. Staff will evaluate scoping comments and develop the assessment with state and federal cooperating agencies under FERC’s Parts 157 and 380 procedures.

In Footnote 1 of the schedule notice, Secretary Debbie-Anne A. Reese said the McNew plant is a “proposed new combined-cycle turbine generating facility,” correcting an earlier description of it as a conversion of an existing facility.

Under 18 CFR 157.22(a), other federal agencies and state agencies administering federally delegated programs must issue final decisions on required authorizations within 90 days after the staff document, unless federal law sets another schedule. Sept. 5 is therefore an interagency permitting deadline, not a construction or commercial-operation date.

For pipeline planners, the schedule supplies a dated benchmark for reliability modeling and interagency permitting.

What would Southern Star build?

Up to 123,000 MMcf/d — 123 billion cubic feet per day — of firm natural-gas transportation would run from Southern Star’s mainline to Evergy Kansas Central Inc.’s planned McNew Power Plant in Reno County. The Hutch Post reported that the proposed $1 billion combined-cycle station is among Reno County’s largest infrastructure investments and is designed for 705 to 765 MW to support regional grid reliability. None of that generation capacity is operating yet.

The certificate filing defines five physical work packages:

  • Line RE lateral: A new 1.6-mile-long, 30-inch-diameter transmission lateral would connect a new compressor station to the McNew delivery point in Reno County. Its diameter is four inches larger than the existing 26-inch Hugoton Loop Line RA.
  • Hutchinson compressor station: A new greenfield compressor would sit along Southern Star’s existing 26-inch Hugoton Loop Line RA in Reno County.
  • Evergy Meter Station: A new measurement and flow-control station would serve the McNew plant site.
  • Hesston and Stafford modifications: Piping and mechanical adjustments would upgrade existing compressor facilities in Harvey and Stafford counties, respectively.
  • Inspection infrastructure: Southern Star would install a pig launcher and mainline tie-in piping, plus a pig receiver at the Evergy Meter Station, for pipeline integrity management.

Which environmental questions remain unresolved?

FERC began NEPA scoping in autumn 2026 under Part 380. On Oct. 1, FERC invited comments on environmental issues from landowners, government agencies, elected officials, Native American tribes and public-interest groups.

The U.S. Army Corps of Engineers’ Kansas City District said a Department of the Army permit under Section 404 of the Clean Water Act could be required if project work involves dredge or fill in jurisdictional waters.

Local objections covered several parts of the proposal:

  • Jared and Yolanda Oatney, represented by counsel Diana Stanley, raised concerns about pipeline routing, local geology, nearby airfield operations, special-status species and designated critical habitat.
  • Alexia S. Welch focused on groundwater protection, geological hazards, air quality, noise, emergency-response preparedness, land use and cumulative effects from industrial development in the surrounding basin.

What changes for utilities and planners?

For utility planners, the proposal links firm natural-gas supply to dispatch needs as regional transmission operators integrate variable renewable generation. High-efficiency combined-cycle units can provide balancing capacity, so modeling must pair firm fuel-delivery contracts with transmission constraints rather than evaluate pipeline and plant separately.

Energy economists tracking pipeline deliverability and regional balancing can use EIA natural-gas storage data to evaluate how localized expansions affect storage withdrawals and seasonal hub pricing across the Midcontinent market. A high-pressure delivery lateral also provides parameters for modeling linepack and transient pressures during peak winter electricity demand.

At the facility level, large projects increasingly reference ASHRAE Standard 90.1 when assessing administrative building envelopes and auxiliary energy use. Major equipment procurement enters global supply chains, where compliance offices track Trade Agreements Act rules and Foreign-Trade Zone customs procedures for specialized turbines and compression hardware.

What milestones come next?

The schedule establishes this sequence:

  • June 7, 2027: FERC staff issues the environmental assessment for Docket No. CP26-572-000.
  • June-July 2027: A 30-day public comment period follows the assessment’s release.
  • Sept. 5, 2027: The 90-day federal authorization decision deadline expires under 18 CFR 157.22(a).
  • Late 2027: The Commission issues its final decision on Southern Star’s Section 7(c) certificate application.
  • 2028-2029: If approvals arrive, facility construction and tie-in integration proceed.
  • Late 2029-2030: Evergy targets commercial operation of the McNew Power Plant.

The decisive next milestone is FERC’s late-2027 Section 7(c) certificate decision: without it, the 2028-29 construction schedule stays contingent and the proposed 705-765 MW plant remains a target, not operating capacity.

via casrai.org (Source)

More from Elena Vasquez

Elena Vasquez

Show full bio

Senior reporter covering technology and product news in Circular economy and the environmental industry at Circular Wire.

605 articles

Nearby routes

« Previous article