Compliance & Policy
FERC sets 2027 review for Seefeld's Smith Creek hydro surrender
FERC set a March 31, 2027 target for an environmental assessment of Seefeld Corporation's Smith Creek hydro surrender, a zero-protest path to removing a Nooksack River weir.

Waypoints
FERC published the Notice of Intent on November 24, 2026 at 91 FR 75845 for FERC Project No. 5982-001.
Target Environmental Assessment issuance date is March 31, 2027, followed by a mandatory 30-day comment period.
Seefeld filed its surrender application July 27, 2026; FERC accepted it August 18, 2026 with zero protests or interventions.
The decommissioning plan records zero streambed excavation, with removals confined above the ordinary high-water mark.
The project holds a license exemption available to hydro facilities under 10 megawatts, on private land in Whatcom County.
FERC published a Notice of Intent on November 24, 2026 (91 FR 75845) that sets a March 31, 2027 target date for an Environmental Assessment of Seefeld Corporation's surrender and complete decommissioning of the Smith Creek Hydroelectric Project in Whatcom County, Washington. The proceeding covers FERC Project No. 5982-001, a small run-of-river facility on Smith Creek inside the Nooksack River watershed.
Seefeld filed its surrender application on July 27, 2026. FERC accepted the application for filing on August 18, 2026 and opened a window for comments, protests and motions to intervene. Nobody intervened, and the Commission logged zero protests, which leaves the environmental review uncontested and sets the schedule for an EA under 18 CFR Part 4 Subpart K and Part 380. The docket carries NEPA tracking ID EAXX-019-20-000-1793782217.
What is Seefeld surrendering?
The company holds a license exemption rather than a standard hydroelectric license. Federal energy statutes in 16 U.S. Code Chapter 12 Subchapter I let projects under 10 megawatts obtain exemptions from multi-decade commercial licensing, but surrender still requires Commission authorization, so FERC must confirm that abandonment does not degrade public waterways or leave structural hazards behind. Under 18 CFR Part 4 Subpart K, exempt facilities "remain subject to Commission compliance orders during decommissioning," so staff will weigh the stability of remaining foundations, the risk of uncontrolled sediment release and the restoration of natural surface-water gradients. The project sits entirely on private land, with no federal holdings in the footprint, which narrows jurisdictional questions but concentrates the review on surface hydrology and fish passage.
The takeaway is simple: Seefeld cannot simply walk away. It needs a federal sign-off that the site will not become a hazard.
How does the plant come apart?
Seefeld's plan dismantles the facility without putting excavators in the active channel. The filing calls for removing the concrete diversion weir, severing the intake pipe "strictly above the ordinary high-water mark," and filling the severed conduit with concrete so it cannot pipe through the bank or collapse. Crews would also demolish the project settling tank, remove the electrical generation machinery, disconnect the site permanently from the regional transmission grid and dismantle the timber-frame portions of the powerhouse. The docket records a construction footprint of zero streambed excavation, with removals isolated above the high-water line.
The takeaway: Seefeld proposes to pull the barrier out from dry ground and seal the conduit rather than dig the channel apart.
What does the docket calendar look like?
- FERC Project No. 5982-001 — small-hydro surrender proceeding under 18 CFR Part 4
- Surrender application — filed July 27, 2026
- Acceptance notice — issued August 18, 2026; zero protests or intervention requests
- Notice of Intent — published November 24, 2026 at 91 FR 75845
- Target Environmental Assessment issuance — March 31, 2027
- Public and agency comment period — 30 calendar days after the EA issues
- In-stream construction footprint — zero streambed excavation
- Jurisdictional land status — non-federal private land in Whatcom County
Why does the Nooksack watershed matter?
Smith Creek sits in a micro-catchment within the Nooksack drainage, which drains the glacier-fed slopes of Mount Baker and empties into Bellingham Bay in northern Puget Sound. The system provides spawning, rearing and migratory corridors for anadromous species: Puget Sound Chinook salmon, listed as threatened under the Endangered Species Act, plus coho, chum and pink salmon, winter-run steelhead and bull trout.
Even a modest low-head weir fragments that connectivity. Such structures block upstream juvenile migration during low-flow periods, warm water behind impoundments and trap the coarse gravel salmon need for redds. Removing the weir and plugging the diversion conduit above the water line would re-establish natural bedload transport and delete one artificial barrier. The excavation limit matters as much as the removal: heavy machinery working an alluvial bed raises turbidity, resuspends silt that can suffocate incubating eggs and destabilizes macroinvertebrate communities.
The takeaway: the restoration case is fish passage and sediment movement, and Seefeld's design choice is to keep machinery out of the gravel.
Who is weighing in on the plan?
FERC project coordinator Rebecca Martin and staff from the Office of Public Participation run the review under 18 CFR Part 380, the Commission's National Environmental Policy Act procedures. The agency has lined up consultation with the Washington Department of Fish and Wildlife, the Washington Department of Ecology, the U.S. Fish and Wildlife Service, NOAA Fisheries and local treaty tribes, including the Lummi Nation and Nooksack Indian Tribe, whose usual and accustomed fishing grounds cover the basin. Reviews must address cumulative effects on surface water quality, riparian microclimate and cultural resources. Staff also draw on baseline discharge data from platforms such as HydroSource and regional hydrographic networks like HydroSHEDS to model how the legacy diversion shaped flows over decades. Comments filed during the 30-day window will shape terms in any final surrender order: site stabilization, revegetation and erosion monitoring.
The takeaway: nobody objected, but four agencies and two tribes will set conditions in the final order.
What happens next?
FERC staff now draft the Environmental Assessment, with a scheduled release of March 31, 2027. Once the EA issues, the Commission opens a mandatory 30-day comment period, and federal, state and tribal entities, academic institutions and members of the public can file substantive scientific and technical comments through the Commission's eFiling portal. Staff fold those comments into the decision record. If the assessment finds no significant adverse environmental degradation, the Commission issues a final surrender order specifying mandatory site stabilization measures, decommissioning deadlines and final inspection sign-offs, then closes the project file.
The economics behind the surrender are not unusual. Small low-head diversions built decades ago often turn uneconomic because of maintenance costs, safety liability and tightening environmental standards, and as snow-fed Pacific Northwest precipitation becomes more volatile, small run-of-river yields grow less predictable. Researchers will also be tracking bedload grain size distribution, pool-riffle morphology and thermal profiles over multiple hydrologic years, data sets that test sediment models and biological recolonization theories.
The milestone that decides the case is March 31, 2027, when the assessment must land and show whether FERC can sign off on a surrender order with binding deadlines or send the project back for more study.