FERC Finds No Significant Impact in Greenup Hydro Relicensing

FERC staff recommend a Finding of No Significant Impact for relicensing the 70.2 MW Greenup hydro plant on the Ohio River, with comments due December 18, 2026 and a final order expected mid-2027.

FERC Releases Environmental Assessment for Greenup Hydroelectric Project Relicensing on the Ohio River
FERC Releases Environmental Assessment for Greenup Hydroelectric Project Relicensing on the Ohio Riveregorshitikov / pixabay

Waypoints

  1. FERC released the environmental assessment on November 24, 2026, recommending a Finding of No Significant Impact for the 70.2 MW Greenup project.

  2. The City of Hamilton, Ohio and AMP seek a new license under docket P-2614-042 for the plant at Greenup Locks and Dam on 12.74 acres of federal land.

  3. Staff require dissolved oxygen monitoring against the ORSANCO 5.0 mg/L daily minimum, with spillway aeration as backup.

  4. The 24-day public comment period closes at 5:00 p.m. ET on December 18, 2026.

  5. A final Commission licensing order is anticipated in mid-2027.

FERC staff have concluded that continued operation of the 70.2-megawatt Greenup Hydroelectric Project will produce no significant environmental impact, provided the applicant adopts staff-recommended protection measures. The Commission published the notice of availability for its environmental assessment on November 24, 2026, opening a 24-day public comment window on the Ohio River facility's relicensing.

The City of Hamilton, Ohio and American Municipal Power, Inc. (AMP) filed the application jointly under Project No. 2614-042, seeking a new major license for the run-of-the-river plant. The facility sits at the U.S. Army Corps of Engineers' Greenup Locks and Dam, occupying 12.74 acres of federal land across Scioto County, Ohio and Greenup County, Kentucky. The powerhouse houses three horizontal bulb turbine-generator units of 23.4 MW each, and the plant has operated continuously since the early 1980s under its original 50-year license.

Commission staff in the Office of Energy Projects recommended a Finding of No Significant Impact under the National Environmental Policy Act, concluding that relicensing with the proposed measures would not constitute a major federal action significantly affecting the quality of the human environment. The NEPA tracking identifier is EAXX-019-20-000-1769181282.

What does the assessment require?

Because the plant draws flow through an auxiliary bypass canal adjacent to the navigation locks rather than across the full river section, staff attached specific operational constraints.

  • Run-of-the-river operation, holding strictly to navigation pool elevations.
  • USACE Section 4(e) conditions for land stewardship and erosion control on the federal footprint.
  • Continuous seasonal dissolved oxygen monitoring in the forebay and tailrace, with supplemental spillway aeration protocols.
  • Trashrack maintenance at the existing 3.5-inch clear bar spacing, with velocity monitoring and fish impingement tracking.

Dissolved oxygen drove much of the analysis. The Ohio River Valley Water Sanitation Commission (ORSANCO) sets a basin-wide minimum daily average of 5.0 mg/L, and during low-flow summer periods turbines drawing intermediate pool waters can depress tailrace oxygen saturation. The assessment recommends a mandatory Water Quality Monitoring and Management Plan to satisfy ORSANCO standards and state Clean Water Act Section 401 certifications. Automated sensors would record DO and temperature continuously; if concentrations approach regulatory thresholds, operators must adjust generation dispatch, run turbine aeration mechanisms, or coordinate with the Corps to increase aerating spill over dam gates.

Fish entrainment and turbine mortality received detailed evaluation as well. Sauger, walleye, freshwater drum, channel catfish and paddlefish traverse the pool. Staff found the 3.5-inch trashracks exclude adult fish, while the bulb turbines' low rotational speeds limit blade-strike injuries for smaller fish. Stable sediment transport and tailrace hydraulics are expected to protect downstream unionid mussel beds, including the endangered fanshell and sheepnose mussels, from scouring or siltation.

Who controls river flows?

Jurisdiction at Greenup is dual. Under Section 4(e) of the Federal Power Act, 16 U.S.C. 797, FERC licenses projects on navigable waters but must incorporate mandatory conditions set by the custodial federal agency. Commercial navigation, managed by the Corps' Huntington District, retains operational primacy. In extreme hydrological deviations or navigation maneuvers, Corps lockmakers can direct flows through dam spillways rather than the turbines.

The renewal proceeds under Section 15 of the Act, 16 U.S.C. 808, which mandates comprehensive environmental re-evaluation before a new license term. Staff conducted the assessment under 18 CFR Part 380, weighing whether an Environmental Impact Statement was warranted or whether mitigation justified a no-impact finding. They chose the latter.

What happens next?

Comments close at 5:00 p.m. Eastern Time on December 18, 2026. Submissions must reference docket number P-2614-042 on the first page. FERC encourages electronic filing through its eFiling portal or the eComment system, which accepts text entries up to 10,000 characters; paper filings may go to Secretary Debbie-Anne A. Reese in Washington, DC, or by commercial delivery to Rockville, Maryland. Project inquiries can go to FERC environmental project managers Patrick Ely and Casey Knight or the Office of Participation.

After the window closes, staff will review public and agency submissions, evaluate any supplementary ecological data and finalize recommendations. A final Commission licensing order establishing binding operational, water quality monitoring and Corps navigation coordination requirements is anticipated in mid-2027. That order is the milestone that determines whether the 70.2 MW plant runs on a new multi-decade term and under what DO and fishery conditions.

via casrai.org (Source)

More from Rebecca Stone

Rebecca Stone

Show full bio

News editor covering companies, deals and strategy in Circular economy and the environmental industry at Circular Wire.

585 articles

Nearby routes

« Previous articleNext article »