Compliance & Policy
FERC Clears Path for 17.2-Mile WBI Energy Gas Lateral in North Dakota
FERC's environmental assessment for WBI Energy's 17.2-mile Line Section 32 lateral finds no significant impact with mitigation, moving 190,000 Dth/day of firm capacity toward approval. Comments close December 23, 2026.

Waypoints
FERC issued the environmental assessment notice on November 27, 2026, with comments due December 23, 2026
The Line Section 32 project spans 17.2 miles of 24-inch pipe in Williams and McKenzie Counties, ND
Capacity totals 190,000 dekatherms per day of firm gas for Basin Electric's planned Bison Generation Station
Docket is CP26-158-000; the timely intervention deadline has expired, leaving only out-of-time motions under 18 CFR 385.214
Staff recommend a Finding of No Significant Impact with mitigation measures
FERC staff have concluded that 17.2 miles of new interstate natural gas pipeline in North Dakota would not significantly affect the human environment, setting up a Finding of No Significant Impact — if WBI Energy follows staff-recommended mitigation. The environmental assessment, noticed in the Federal Register on November 27, 2026, gives the Line Section 32 Expansion Project its clearest regulatory signal yet. Public comments close at 5:00 p.m. Eastern on December 23, 2026.
Here's what the project actually is. WBI Energy Transmission, headquartered in Bismarck, filed a certificate application under Docket No. CP26-158-000 to build, install and operate transmission lateral facilities across Williams and McKenzie Counties. The driver: up to 190,000 dekatherms per day of incremental firm transportation capacity for Basin Electric Power Cooperative's planned Bison Generation Station, a regional gas-fired plant backing grid reliability for rural electric cooperatives across the Upper Midwest.
What does the filing specify?
The Commission's document lays out five concrete components:
- Lateral pipeline section — 17.2 miles of 24-inch diameter steel pipe in Williams County, delivering firm supply to the Bison Generation Station.
- System interconnect — a high-pressure tie-in assembly in Williams County linking the lateral to WBI Energy's existing transmission network.
- Northern Border interconnect — bidirectional flow with overpressure protection in McKenzie County, for system flexibility and inter-pipeline pressure control.
- Delivery meter station — an ultrasonic custody transfer meter skid in Williams County for measurement at the power station.
- Capacity allocation — 190,000 dekatherms per day of firm interstate capacity.
For scale, 17.2 miles of 24-inch pipe is a modest lateral by interstate standards — this is a connecting line to a single power station, not a trunkline build. But it still crosses the full Section 7(c) Certificate of Public Convenience and Necessity process under the Natural Gas Act of 1938, which requires FERC to weigh market demand contracts and land disturbance against cumulative environmental footprint.
How thorough is the review?
Staff ran the assessment under 18 CFR Part 380, the Commission's NEPA-implementing regulations. The analysis covered soil erosion, prairie ecosystem disruption, aquifer crossing safeguards, greenhouse gas emissions and cultural resources, with the record tracked under NEPA document ID EAXX-019-20-000-1778150426. Staff examined construction disturbance footprints, agricultural topsoil segregation, horizontal directional drilling protocols across sensitive watercourses, and operational emissions. On indirect and cumulative effects, the review assessed GHG emissions from both compressor operations and upstream resource extraction.
Federal coordination also folded in EPA NEPA review guidance covering air quality attainment thresholds, stormwater permitting and species conservation across western North Dakota.
Who can still weigh in?
Three channels remain open until the December 23 deadline: eComment on the FERC Online portal for short text comments; eFiling for formal briefs, technical affidavits, geospatial exhibits and reports; and postal mail to Commission Secretary Debbie-Anne A. Reese in Washington, D.C., or courier delivery to the Commission's Rockville, Maryland facility.
Here's the catch for practitioners. Filing environmental comments does not grant intervenor status, and the deadline for timely intervention in Docket CP26-158-000 has already passed. Any landowner, NGO or research institution wanting party status — the ticket to rehearing requests or judicial review at the U.S. Court of Appeals — must now file a motion for out-of-time intervention under 18 CFR 385.214(b)(3) and (d), and demonstrate good cause for arriving late.
What happens next?
After the comment window closes, FERC environmental staff will review submitted technical filings, citizen critiques and agency correspondence, and prepare responses to substantive arguments for the Commissioners. The Commission will then issue a formal order on whether the project meets the public convenience and necessity standard under Section 7. If approved, the order will set binding environmental conditions WBI Energy must satisfy before receiving notice to proceed with ground disturbance in Williams and McKenzie Counties.
That final certificate order — and the conditions attached to it — is the milestone that decides whether shovels hit the ground.